1.3 SUBMITTALS <br /> A. The OWNER will submit the preconstruction survey to the EARTHWORK <br /> CONTRACTOR and QA/QC CONSULTANT at least two days before the <br /> scheduled start date of the Work. The preconstruction survey will be depicted on <br /> the Construction Drawings grading plan in a screened font. <br /> B. The OWNER will prepare as-built survey drawings for WMU FU-03 liner <br /> construction for the top of clay liner, top of granular drainage material, and top of <br /> protective operations layer. The as-built drawings will be prepared at a 1:50 scale <br /> and will depict the prominent layer with the preceeding layer in a screened font. <br /> Grid points and elevations of both the prominent and preceeding layer will be <br /> shown. A table listing northings, eastings, and elevations of the coordinate points <br /> will also be included on the drawing. <br /> C. The results of the WMU FU-03 top of clay liner, top of granular drainage layer, <br /> and top of protective operations layer surveys will be provided to the QA/QC <br /> CONSULTANT within two days of the survey for approval prior to placing <br /> overlying materials. The QA/QC CONSULTANT shall have two working days to <br /> review survey results and may independently verify survey results. The time <br /> taken by the OWNER to perform the survey and by the QA/QC CONSULTANT <br /> in checking and verifying the survey results will be considered included in the <br /> total calendar days allotted the EARTHWORK CONTRACTOR before liquidated <br /> damages are assessed. <br /> 1.4 PRECONSTRUCTION SURVEY <br /> A. The OWNER will perform a preconstruction survey in all areas identified by the <br /> DESIGN ENGINEER as having been modified from the topography depicted on <br /> the Construction Drawings. <br /> B. The preconstruction survey will be performed at a minimum 100-ft grid, delineate <br /> all break points and significant features, and be of sufficient detail to create a <br /> topographic map suitable for volume calculation purposes. <br /> 1.5 SURVEYS FOR LAYOUT AND PERFORMANCE OF WORK <br /> A. The EARTHWORK CONTRACTOR shall perform all surveys for layout and <br /> performance of the Work, reduce the field notes, and make necessary calculations <br /> for performance of the Work. <br /> 1.6 AS-BUILT SURVEY DRAWINGS—WMU FU-03 <br /> A. The OWNER will establish a 75-foot reference grid for verifying minimum slope <br /> grades and for thickness determinations of overlying layers of the lining and LCRS <br /> systems. Survey measurements shall be taken at the same reference grid points for <br /> each succeeding layer. <br /> B. The EARTHWORK CONTRACTOR shall notify the OWNER at least 3 working <br /> days in advance of when a layer is completed and ready for as-built surveys. The <br /> OWNER will perform the as-built survey within two days of the layer being <br /> completed. The results of the top of clay liner, top of granular drainage layer, and <br /> top of protective operations layer surveys will be provided to the QA/QC <br /> CONSULTANT within two days of the survey for approval prior to placing <br /> overlying materials. The QA/QC CONSULTANT shall have two working days to <br /> FORWARD LANDFILL 01410 <br /> 2 SURVEYS <br />