tl"YTOR <br /> ENGINEERING, INC. <br /> DAILY CONSTRUCTION FIELD REPOR <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 021605.03 45 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca, Ca Butch Stefan Forward, Inc. October 28,2003 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: <br /> Sukut Construction GSE San eeta Lewis <br /> General Foreman: Liner Superintendent: Other: <br /> Jim Hasal Are Khounmouan <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> On site native, stockpiled, light brown silty Warm,clear and Ken Davila <br /> CLAY breezy <br /> Equipment on site: <br /> 1-D6 dozer 1-water truck, 1-633 scra er 1- 16G blade, 1-backhoe, 1-trencher, 1-825 aomactor <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> On site today for observations and testing at the location listed above. I met with Jim H. (Sukut <br /> superintendent)in the early morning to discuss the proposed plan of operation. General earthworks <br /> operations would continued with the one(1) scraper hauling minor amounts of excess clay from the <br /> windrows generated by the blade. The one(1)blade continued to finish cut the clay on the north cell floor <br /> with the smooth edges. The D6 dozer cleaned and widened the access road into the cell that will be used fo <br /> general truck access with the sheepsfoot compactor applying compactive effort. The backhoe and trencher <br /> continued excavating the anchor trench around the lechate pond. <br /> Review of the roll certifications of the sixteen ounce(16oz)geotextile,twelve-ounce (12oz.)geotextile, <br /> eight-ounce(8oz) geotextile and the geonet began as the Bentofix GCL material review was completed. <br /> By the late afternoon, nothing had been heard about the sump survey subgrade acceptance. <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev. 0 1 of 1 <br /> r-,7 <br />