LT TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. ReportSequence <br /> Forward WMU FU-06 02.1605.07 63 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste August 8, 2006 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, It. breeze (NW), mid 50's to low 90's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor, 2 water trucks, excavator,rock truck, loader,backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn Construction continued finish-grade work on compacted Clay Liner in the floor area and within <br /> the sump. <br /> 2. Contractor excavates the anchor trench across the north-end of the Southern Portion at the top of the <br /> 5:1 slope. <br /> II. Testing <br /> 1. Monitored activities as needed. <br /> 2. Continued laboratory testing on field samples. <br /> III. Conversations <br /> • None listed. <br /> C=_'N I I P 1 0 <br /> Prepare B Reviewed By: Al <br /> 1 of 1 4/23/03,Rev.0 <br />