Laserfiche WebLink
17E TOR <br /> ENGINEERING,INC. <br /> ® DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 84 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste September 5, 2006 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, it. breeze (N ), low 60's to high 90's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor, 2 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. GSE completed vacuum testing repairs to the 60-mil HDPE single-side textured liner on the 5:1 slope area <br /> in the Southern Portion on module FU-06. <br /> 2. GSE continue deployment of Geocomposite on the western portion of the 5:1 slope area. <br /> 3. Gwinn Construction continued moisture conditioning the floor area Clay Liner. <br /> esting <br /> Monitored activities; all logs, as-built, etc. <br /> I1I. Conversations <br /> • None listed. <br /> Prepared>3y: Reviewed By: G <br /> 1 of 1 4/23/03,Rev. 0 <br />