Laserfiche WebLink
17E TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 85 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste September 6, 2006 Wednesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, It. breeze (NW), low 60's to mid 90's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor,2 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. GSE completed deployment of Geocomposite on the 5:1 slope area in the Southern Portion of FU-06. <br /> 2. GSE does extra work to make a repair to the primary liner in the northeast area of the 5:1 slope in module <br /> FU-05, by applying a 4'x 4' patch using extrusion welding methods and vacuum testing the repair to verify <br /> "no leaks." GSE also replaced an approximately 20' x 60' portion of Geocomposite here. (photos taken) <br /> I GSE prepares to deploy 60-mil double-side textured HDPE on the floor of the Southern Portion of FU-06. <br /> 4. Gwinn Construction continued moisture conditioning the floor area Clay Liner. <br /> 5. Gwinn Construction set the HDPE riser pipe for the secondary liner in the sump <br /> II. Testing <br /> 1. Monitored activities as needed. <br /> 2. Completed data entry for the Deployment and Seaming/Air Testing Logs. <br /> III. Conversations <br /> ® None listed. <br /> Prepared y. Reviewed By: �l <br /> 1 of 1 4/23/03,Rev. 0 <br />