117 <br /> E 'TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 97 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste September 20, 2006 Wednesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: :QA Technician: <br /> Native soils Scat. clouds, v. windy(NW), high 50's to high 70's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor, 2 water trucks, excavator,rock truck, loader, backhoe; forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn continued placement of the 1' thick lift of LCRS Granular Drainage material on the east floor area. <br /> 2. Gwinn continued deployment of 8 oz. Filter Geotextile and placement of the Operations Layer over <br /> geotextile down the east side of the floor area. Work reached the temporary berm in the SEC today. <br /> 3. The D6 backfills the anchor trench on the south slope. <br /> II. Testing <br /> 1. Monitored activities. <br /> 2. Completed misc. field data to Deployment, Seaming and Air Testing Logs. <br /> 3. Completed data entry on the Deployment Logs. <br /> III. Conversations <br /> • None listed. <br /> Prepared)3y: Reviewed By: . <br /> 1 of 1 4/23/03,Rev.0 <br />