Laserfiche WebLink
E VTOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 111 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste October 10, 2006 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, breeze (SE), low 50's to mid 70's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 1 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn constructs the berm at the top of the south slope in the Southern Portion of WMU FU-06. <br /> 2. Gwinn trims excess HDPE liner from the north and south slopes of the east termination in the Southern <br /> Portion of WMU FU-06 in preparation to place grout in slope anchor trench. <br /> 3. Vector Engineering, Inc. continued and completed leak testing the floor area of the WMU FU-06 Southern <br /> Portion: no leaks were found. <br /> 4. Gwinn completed detail on earthwork at the top of the 5:1 slope/tie-in to the upper deck Northern Portion <br /> of WMU FU-06. <br /> lI. Testing <br /> 1. Monitored activities. <br /> 2. Continued work on the Final Report. <br /> I1I. Conversations <br /> • None listed. <br /> Prepared B Reviewed By: <br /> 1 of 1 4/23/03,Rev.0 <br />