117 <br /> E TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 113 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste October 12, 2006 Thursday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear,breeze (SE), low 50's to mid 70's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 1 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn continued and finished deployment of 8 oz. Filter Geotextile and placement of the Operations <br /> Layer soils along the tie-in between FU-06 and FU-05. <br /> II. Testing <br /> 1. Monitored activities. <br /> 2. Continued work on the Final Report. <br /> III. Conversations <br /> • Left a message with Jerry Slinkard with GSE requesting inventories on the Geo-grid delivered to <br /> site. <br /> Prepared B <br /> P Y Reviewed By: C <br /> 1 of 1 4/23/03,Rev.0 <br />