17E TOR <br /> ENGINEERING,INC. <br /> ® DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 26 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste June 19, 2006 Monday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> I rt Clear, It. breeze (N ), high 50's to low 90's Mike Strobel <br /> Equipment on site: <br /> 3x637 scrapers, D6 dozer, 815 compactor, water truck, excavator,rock truck, loader, backhoe <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Continued rough grading in the south east area of FU-06. <br /> 2. Continued excavation to make the south end of FU-06. Soil materials being placed and compacted <br /> outside the east limit of FU-06. <br /> I. Testing <br /> 1. Took one FDT in compacted Subgrade in the east floor area of FU-06; test SG-77 passed. <br /> III. Conversations <br /> • With Larry Simms, Gwinn Construction, re: Has the survey of the north area of FU-06 been <br /> reviewed? In a call to Monte Christie, Vector Engineering, Inc., Monte said he had not seen the <br /> survey, but if Larry Simms felt comfortable he could start installation of the LCRS system here. <br /> Prepared B7) Reviewed By: OlC <br /> 1 of 1 4/23/03,Rev.0 <br />