Forward Landfill <br /> Gas Probe Monitoring Report <br /> on conditions at each location with the screened section being installed from this point <br /> to the bottom of the probe. <br /> A granular filter pack consisting of No. 3 Monterey type sand was placed in the annular <br /> space between the screen and the borehole wall. Filter pack was placed in each boring to <br /> approximately 1 foot below the bottom of the screen and 0.5 foot above the top of the <br /> screen. A low permeability seal, consisting of a minimum of 5 feet of Enviro-Plug medium <br /> bentonite chips, was placed immediately above the filter pack. Construction details are <br /> shown on the Boring Logs and presented on Table 1. <br /> Prior to start of drilling operations, the ground surface at each proposed probe location <br /> was surveyed for elevation and location (Table 1). Probe locations were not changed <br /> from those proposed. <br /> SURFACE COMPLETIONS <br /> After the monitoring probes were installed, BAS returned to the Forward Landfill on <br /> October 2, 2009 to complete the surface monuments. Surface completions included a <br /> 3 foot raised steel monument placed over the probe casing and embedded into a <br /> concrete apron. The monument lid was secured with a padlock. Bollards were placed <br /> around the pad protecting the monument from vehicular traffic. <br /> CONCLUSION <br /> Two 2 new perimeter landfill as monitoring robes were installed at the Forward <br /> ( ) p g gp <br /> Landfill site to bring the existing perimeter probe network into compliance with current <br /> Title 27 requirements. Figures, tables and boring logs included as attachments to this <br /> report demonstrate the compliance of the newly installed network. <br /> 4 BRYAN A.STIRRAT S ASSOCIATES <br /> (J:\Republic Services\Forward\2009.0087 Probe CQA\Report\Probe Installation Report.docm:01/19/10) <br />