Geo-LoqkA S S O C I A T E S <br />CQA DAILY SUMMARY REPORT #051 <br />T — <br />REPUBLIC SERVICES FORWARD LANDFILL, FU -13 <br />• CQA personnel monitored the placement of the coarse drainage gravel in the LCRS trenches and the <br />granular drainage layer along the top of the north slope, top deck area; insured that proper procedures were <br />used to prevent damage to the underlying synthetic liner. <br />Meetings and Site Discussions: <br />• Met with Jose Gutierrez (Comanco Superintendent) in the morning to discuss planned activity for the work <br />shift. The Contractor would complete installation filter fabric on the upper slope. The Contractor would <br />demobilize upon completion of a final walk with CQA personnel. <br />• Met with Kevin Turner (Guinn Superintendent) in the morning to discuss planned activity for the work shift. <br />The Contractor would install drain gravel unloader and make preparations for hauling and placement of the <br />drainage gravel layer on the south half of the Cell floor. The Contractor would complete excavation and <br />backfill of the liner anchor trench at top of the North Slope, east end. The Contractor would continue <br />placement of coarse drainage gravel material in east LCRS trench and in sumps. <br />• CQA personnel attended the weekly project progress meeting held in the front entrance facility; refer to the <br />CQA project progress meeting minutes. • <br />Site Visitors: <br />• None <br />Photos: <br />Fig.1 Looking west on east side of upper deck area in FU 13, liner anchor trench excavation. <br />