2. Review of work progress since previous meeting: 40 <br />- Guinn completed the main slope anchor trench and 2:1 slope anchor trench <br />excavation. <br />- Guinn removed overburden and excavated and processed clay material from the <br />location further to the east. The clay is being placed in a stockpile. Approximately <br />14,240 cy have been moved with an additional 6,900 cy of overburden. <br />3. Projected schedule: <br />- Guinn will continue to haul, moisture condition, and stockpile clay. <br />- Guinn will excavate and remove the existing LCRS sump. Guinn with coordinate <br />with Republic for leachate removal and may pump ahead of the sump and remove <br />leachate from the LCRS pipe. <br />- Guinn is set up to do the off loading of the geosynthetics. <br />- Comanco will place liner starting on July 2"d. Comanco will fill sandbags on July <br />1St and Guinn will have the clay completed at the toe of the slope. <br />- The Geogrid should be arriving this week. <br />- Guinn will revise their construction schedule to show clay being placed in two <br />phases. <br />4. Field observations, problems, conflicts, and changes: <br />- GLA stated that Guinn needs to keep the maximum amount of moisture in the <br />clay in order to obtain the required permeability values. <br />- GLA is currently running the first clay stockpile permeability evaluation test at <br />90% compaction and 3% over optimum moisture. The results will be transmitted as <br />soon as they are available. <br />- Guinn will need to proof roll the subgrade prior to liner placement. <br />5. Issues which impede the construction schedule and corrective measures: <br />- GLA just received samples of the geosynthetic materials and will be running large <br />scale direct shear testing on the specified interfaces. This information is critical for <br />the delivery of materials from the manufacturers. <br />6. Review of submittals and RFI's: <br />- Submittal S -01A was provided by Guinn and was approved by GLA for the HDPE <br />pipe. <br />- Guinn provided the leachate tank submittal, S-02. Various options were discussed <br />at the meeting including using a corrugated HDPE pipe with perforations and <br />HDPE plates welded to the top and bottom. Based on the cost and ability to reuse <br />Forward Landfill WMU FU -13 <br />Progress Meeting Minutes Page 2 <br />