TABLE 2 <br /> FORWARD LANDFILL <br /> CLOSURE IMPLEMENTATION SCHEDULE <br /> 187.6-ACRE CLOSURE AREA <br /> TASKS MONTHS <br /> 1 2 3 4 5 6 7 8 9 10 11 <br /> Equipment Mobilization <br /> Site Exploration and Survey <br /> Foundation Layer Preliminary Grading <br /> Placement of the Foundation Layer <br /> Placement of Barrier Layer <br /> Placement of vegetative Layer <br /> Drainage Control System Construction(over refuse) <br /> Gas Extraction System <br /> Demolition <br /> Demobilization <br /> Z:\PROIECTS\Alliedwaste\Forward\Five Year PermkRYw2013VTD-5Yr PR2013\Appendk:es\App A-PCPCMP2013\Table2CIo Impl Scad2008 <br />