Table 6 <br /> Preliminary Closure Cost Estimate <br /> North County Recycling Center and Sanitary Landfill <br /> San Joaquin County, California <br /> Items Quanti Units Unit Cost Subtotals <br /> FINAL COVER SOIL <br /> 1 Preparation of landfill to receive cover(final grading) 185 ACRE $100 $19,000 <br /> 2 Evapotranspiration Layer(on-site soils) 895,400 CY $2 $1,791,000 <br /> ACRE $2,000 $370,000 <br /> 3 <br /> Vegetation 185 <br /> g <br /> L2,180,000 <br /> 00 <br /> I::s:zn:,,i:::Ye3i':eie ,:.:I.:..:.>al.._:::'s::s::'•.r:.»:�.r:.ru::...�.0 <br /> Final Cover Soil Subtotal <br /> MONITORING SYSTEM <br /> 4 Landfill Gas Monitoring System $20,000 <br /> 5 Groundwater Monitoring System $21,000 <br /> ......... $5,000 <br /> Leachate Control System 46,000 <br /> $ <br /> Monitoring in Systems <br /> Subtotal <br /> GAS CONTROL <br /> 7 Disabling and Rebuilding Gas System $990,000 <br /> :. <br /> $255,000 <br /> 8 Addition System <br /> i:...; . <br /> $1,245,000 <br /> ; <br /> .,..:......::....,...........,......;:.:...:.....:........::.::€€ €€s �lil lis€€i;s';;�;s€€ <br /> Gas Control S stem Subtotal ,:..,;I;.::.,:.::.:.:..:.:............... <br /> SITE IMPROVEMENTS <br /> 9 Drainage Structures $50,000 <br /> 10 Security Measures $88,000 <br /> 11 Survey Monuments $36,000 <br /> $150,000 <br /> 12 Dismantic Structures <br /> Decommission Environmental Monitoring System $0 <br /> 13 <br /> 0 <br /> 3 <br /> 24 00 <br /> veme <br /> nt Subtotal <br /> Site Improvement ro <br /> ...::...... <br /> PROFESSIONAL SERVICES $100,000 <br /> 14 Engineering(Design and Bid Documents) $18,000 <br /> 15 Topographic and Boundary Survey $119,000 <br /> 16 <br /> Construction Quality Assurance <br /> :;. <br /> ,i. 00 <br /> 70 <br /> 'ri?iii1'iHbt_iiiii!:::-.::!::::!:!::!::.�s::::,:�:r.'�::....,,.�,".. , <br /> Professional Services Subtotal "" "" """ <br /> .... ...:::.:.:,::::.. <br /> $4,780,000 <br /> TOTAL ESTIMATED CLOSURE COST <br /> $956,000 <br /> CONTINGENCY(20%) <br /> TOTAL $55,,736736,,000 <br /> sf=Square Foot <br /> CY=cubic yard <br /> LS=lump sum <br /> All Costs are in 2004 dollars. <br /> FINAL COVER-Assume EI cover 3 feet thick. <br /> MONITORING SYSTEM <br /> 4 Assume three new gas monitoring wells will be installed. Each will consist of 3 probes(Cost per Spectrum Exploration). <br /> 5 Assume two new groundwater monitoring wells will be installed. In addition,this cost should cover repairs to all of the wells <br /> at closure(cost per Spectrum Exploration). <br /> 6 It is anticipated that the leachate system will be installed as each module is constructed. However,this cost will cover any <br /> additional repairs or additional sumps,as needed. <br /> GAS CONTROL-Assume the cost to install the system is$3.3 million. This would be installed during the active life of the <br /> landfill. At closure,it was assumed that approximately 1/3 of the system will need to be rebuilt plus an additional 17 acres <br /> constructed. <br /> SITE IMPROVEMENT <br /> 9 Drainage Structures consist of perimeter ditching and natural finished drainage contours on the landfill surface. <br /> 10 Fencing will be placed around the entire site as it is developed. Should the landfill close at tany time,the cost for closure <br /> includes approximately 2,500 feet. Assume aluminized steel,3 strands,8 feet high. <br /> 11 Assume 6 survey monuments. <br /> 12 Structures to be removed include the scalehouse,office and maintenance buildings. These account for 43,210 sf(based on <br /> 1990 PCPC Plan)Demolition cost assumes buildings on 4"concrete slab(R S Means,2004). <br /> 13 Dismantling of environmental control system will be included in the post-closure costs. <br /> PROFESSIONAL SERVICES <br /> 14 Assume engineering costs= 1%of Services(R S Means,2004). <br /> 15 Assume conventional topographical survey+aerial surveying at 1'intervals. Cost based on maximum topographic curvey <br /> cost per R S Means,2004. <br /> 16 CQA costs are estimated as 5%of cover material placement. <br /> North County RC and SL Public Works/Solid Waste <br /> JTD County of San Joaquin-November 30,2004 <br />