KLEINFELDER <br /> content of between 20 to 22 percent. If, for example, a work area measuring 400 x 50 feet <br /> was considered, a compacted thickness of 12 inches proposed, and for the laboratory <br /> maximum density of 120 per square foot (psf) (the actual in-place dry density would be <br /> approximately 95 percent of the standard), we calculate that 14 to 15 truckloads per section <br /> would be neede d to comply with the 20 percent Ione clay requirement. We note, however, <br /> that the actual spread calculations must be made during construction when equipment type <br /> is known and the moisture content of Ione clay confirmed. Due to the consequences of <br /> having the barrier layer fail the CIWMB and RWQCB regulations, it is important that the <br /> evaluation of the clay spread be conservative. <br /> In addition to the activities described above, the following specifications shall be followed <br /> during construction: <br /> (a) If the barrier layer is constructed in multiple lifts and is allowed to dry between lifts, <br /> the surface of each successive lift shall be scarified to a depth of two inches before <br /> the placement of the next loose lift. The purpose of the scarification is to improve <br /> bonding between successive lifts. <br /> (b) Equipment or truck traffic on the scarified surface shall not be permitted during the <br /> period between scarifying and the placement of the following lift. <br /> (c) Each lift shall be thoroughly compacted and satisfy moisture/density, and <br /> F'T permeability controls before a subsequent lift is placed. <br /> is <br /> (d) Compaction of lifts shall be performed with an appropriately heavy, properly <br /> ballasted, penetrating foot compactor CAT 815 (or equivalent, subject to approval <br /> by the Engineer). <br /> L (e) The daily work area shall extend a distance no greater than permits the <br /> maintenance of moist-soil conditions and construction operations. Desiccation and <br /> crusting of the lift surface shall be avoided as much as possible. <br /> (f) If desiccation and crusting of the lift surface occurs, the desiccated zone shall be <br /> removed and the exposed surface shall be scarified and moisture conditioned before <br /> remediation filling and compacting or subsequent filling and compaction is <br /> L permitted. <br /> CR9-42 Page 20 of 28 <br /> Copyright 1991 Kleinfelder, Inc. <br />