LFR Inc.
<br /> 35 September 7,-2005 - Work Plan for Installing Groundwater Monitoring Well
<br /> MW-06 at the Tracy Tire Fire Site, Former Royster Tire Facility, Tracy
<br /> California
<br /> 36 September 8, 2005 - Temporary Retention Pond Construction and Planned
<br /> Excavation at the Tracy Tire Fire Site, San Joaquin County, California
<br /> 37 November 30, 2005 - Project Status Report, Tracy Tire Fire Site, San Joaquin
<br /> County, California
<br /> 38 November 30, 2005 - Alternatives for Addressing Long-Term Groundwater
<br /> Mitigation at the Tracy Tire Fire Site, San Joaquin County, California
<br /> 39 November 30, 2005 - MW-6 Groundwater Sampling Results, Tracy Tire Fire
<br /> Site, San Joaquin County, California
<br /> 40 January 9, 2006 - Evaluation and Recommendations Concerning Cut Slope
<br /> Stability, Tracy Tire Fire Site, Tracy, California
<br /> 41 February 15, 2006 - Excavation of Pyrolytic Oil-Affected Soil Including the
<br /> Construction, Use, and Destruction of a Temporary Retention Pond at the Tracy
<br /> Tire Fire Site, San Joaquin County, California
<br /> 42 February 24, 2006 - Work Plan for Installing Groundwater Monitoring Well
<br /> MW-8 at the Tracy Tire Fire Site, Former Royster Tire Facility, San Joaquin
<br /> County, California
<br /> 43 April 6, 2006 - Additional Soil and Groundwater Investigation and Monitoring
<br /> Well Installation Report for the Tracy Tire Fire Site, Former Royster Tire
<br /> Facility, Tracy, California
<br /> 44 May 24, 2006 - Well Destruction Report for Groundwater Monitoring Well
<br /> MW-6, Tracy Tire Fire Site, Former Royster Tire Disposal Facility, Tracy,
<br /> California
<br /> 45 May 31, 2006 - Monitoring Well MW-8 Installation Report, Tracy Tire Fire
<br /> Site, Former Royster Tire Disposal Facility, Tracy, California
<br /> 46 May 31, 2006 - Soil Confirmation Sampling Results for Pyrolytic Oil-Affected
<br /> Areas at the Tracy Tire Fire Site, Former Royster Tire Disposal Facility, Tracy,
<br /> California
<br /> 47 June 14, 2006 - Work Plan for Installing, Developing, and Sampling
<br /> Groundwater Monitoring Well MW-9, Tracy Tire Fire Site, Former Royster Tire
<br /> Disposal Facility, Tracy, California
<br /> 48 August 1, 2006 - Groundwater Monitoring Report for Samples Collected During
<br /> June 2006, Tracy Tire Fire Site, Former Royster Tire Disposal Facility, Tracy,
<br /> California
<br /> 49 August 11, 2006 - Monitoring Well MW-9 Installation Report ,Tracy Tire Fire
<br /> Site, Former Royster Tire Disposal Facility, Tracy, California
<br /> Page 8 rpt-RA—summ-Nov06-final-09025:FNC