PERFORMANCE SPECIFICATION
<br />SECTION I GENERAL CONDITIONS
<br />PART 1 - GENERAL
<br />1.1 SCOPE OF WORK: THE WORK INCLUDED IN THE CONTRACT FOR THIS PROJECT CONSISTS OF THE FURNISHING OF ALL
<br />LABOR, MATERIALS, SERVICES, EQUIPMENT AND APPLIANCES REQUIRED IN CONJUNCTION WITH OR PROPERLY INCIDENTAL
<br />TO THE COMPLETE CONSTRUCTION OF A GASOLINE INSTALLATION FOR 7 -ELEVEN, INC.
<br />PART 2 - AGREEMENT
<br />2.1 CONTRACTOR SHALL NOT START WORK WITHOUT CONTRACT AND APPROVED SEALED PLANS.
<br />PART 3 - INTENT OF DRAWING AND SPECIFICATIONS
<br />3.1 THE INTENT OF THE DRAWINGS AND SPECIFICATIONS IS TO PRESCRIBE A COMPLETE WORK OR IMPROVEMENT WHICH THE
<br />CONTRACTOR SHALL PERFORM IN FULL COMPLIANCE WITH THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL
<br />PERFORM ALL WORK NECESSARY TO COMPLETE THE WORK IN A SATISFACTORY AND ACCEPTABLE MANNER.
<br />3.2 THE CONTRACTOR SHALL, UPON DISCOVERY, REPORT ANY DISCREPANCIES IN THE DRAWINGS AND SPECIFICATIONS TO
<br />THE OWNER'S CONSTRUCTION MANAGER.
<br />3.3 THE DRAWINGS AND SPECIFICATIONS ARE INTENDED TO BE COMPLIMENTARY. ANYTHING MENTIONED IN THE
<br />SPECIFICATIONS AND NOT SHOWN ON THE DRAWINGS, OR SHOWN ON THE DRAWINGS AND NOT MENTIONED IN THE
<br />SPECIFICATIONS, SHALL BE OF LIKE EFFECT AS IF SHOWN OR MENTIONED IN BOTH. GENERALLY, THE SPECIFICATIONS
<br />DESCRIBE WORK WHICH CANNOT BE READILY IDENTIFIED ON THE DRAWINGS AND INDICATED TYPES, QUALITIES AND
<br />METHODS OF INSTALLATION OF THE VARIOUS MATERIALS AND EQUIPMENT REQUIRED FOR THE WORK. IT IS NOT INTENDED
<br />TO MENTION EVERY ITEM OF WORK IN THE SPECIFICATIONS WHICH CAN BE ADEQUATELY SHOWN ON THE DRAWINGS NOR
<br />TO SHOW ON THE DRAWINGS ALL ITEMS OF WORK DESCRIBED OR REQUIRED BY THE SPECIFICATIONS EVEN IF THEY ARE
<br />OF SUCH NATURE THAT THEY COULD HAVE BEEN SHOWN THEREON. ALL MATERIALS OR LABOR FOR WORK WHICH IS
<br />SHOWN ON THE DRAWINGS OR IS REASONABLY INFERABLE AS BEING NECESSARY TO PRODUCE A FINISHED JOB SHALL BE
<br />PROVIDED BY THE CONTRACTOR WHETHER OR NOT THE WORK IS EXPRESSLY COVERED IN THE SPECIFICATIONS.
<br />3.4 THE CONTRACTOR, SUBCONTRACTORS AND ALL TRADES SHALL EXAMINE THE SITE AND ASCERTAIN EXISTING CONDITIONS
<br />PRIOR TO THE START OF THEIR PORTIONS OF THE WORK. BEFORE ORDERING MATERIALS OR DOING ANY WORK, THE
<br />CONTRACTOR SHALL VERIFY AND BE RESPONSIBLE FOR THE CORRECTNESS OF ALL MEASUREMENTS AT THE SITE. ANY
<br />DIFFERENCES WHICH MAY BE FOUND BETWEEN ACTUAL DIMENSIONS AND DIMENSIONS INDICATED ON THE DRAWINGS OR
<br />SHOP DRAWINGS SHALL BE SUBMITTED TO THE OWNER'S CONSTRUCTION MANAGER FOR CONSIDERATION BEFORE
<br />PROCEEDING WITH THE ACTUAL DIMENSIONS AND MEASUREMENTS INDICATED ON THE DRAWINGS UNLESS A SUBSTANTIAL
<br />ERROR HAS BEEN MADE. IF SUCH AN ERROR SHOULD OCCUR, IT SHALL BE BROUGHT TO THE ATTENTION OF THE OWNER'S
<br />CONSTRUCTION MANAGER AND RESOLVED BEFORE PROCEEDING WITH WORK.
<br />3.5 THE ORGANIZATION OF SPECIFICATIONS INTO DIVISIONS, SECTIONS AND PARAGRAPHS, AND THE ARRANGEMENT OF THE
<br />DRAWINGS ARE NOT INTENDED TO CONTROL THE CONTRACTOR IN DIVIDING THE WORK AMONG SUBCONTRACTORS OR IN
<br />THE ESTABLISHING THE EXTENT OF WORK TO BE PERFORMED BY ANY TRADE.
<br />3.6 DRAWINGS AND SPECIFICATIONS: DRAWINGS INDICATE GENERAL DESIGN AND ARRANGEMENTS DRAWINGS ARE
<br />DIAGRAMMATIC AND ARE NOT SCALED FOR DIMENSIONS. TAKE ALL DIMENSIONS FROM ARCHITECTURAL PLANS AND
<br />EQUIPMENT TO BE FURNISHED. VERIFY DIMENSIONS IN THE FIELD.
<br />PART 4 - RESPONSIBILITY OF THE CONTRACTOR
<br />4.1 CONTRACTOR HEREBY DECLARES HE HAS READ ALL SPECIFICATIONS AND EXAMINED THE DRAWINGS AND
<br />THAT HE UNDERSTANDS ALL CONDITIONS.
<br />4.2 CONTRACTOR HEREBY DECLARES HE HAS VISITED THE SITE AND IS FAMILIAR WITH THE CONDITIONS
<br />AFFECTING THE WORK. NO ALLOWANCES SHALL BE MADE SUBSEQUENTLY ON BEHALF OF THE
<br />CONTRACTOR FOR ANY ERROR NEGLIGENCE ON HIS PART. IF IN THE PERFORMANCE OF THE CONTRACT,
<br />LATENT CONDITIONS AT THE SITE ARE FOUND TO BE MATERIALLY DIFFERENT FROM THOSE INDICATED
<br />BY THE DRAWINGS AND SPECIFICATIONS, OR UNKNOWN CONDITIONS UNUSUALLY INHERENT IN WORK OF
<br />THIS CHARACTER SHOWN AND SPECIFIED, THE ATTENTION OF THE OWNER'S CONSTRUCTION MANAGER
<br />SHALL BE CALLED IMMEDIATELY TO SUCH CONDITIONS BEFORE THEY ARE DISTURBED.
<br />4.3 CONTRACTOR HEREBY DECLARES THAT HE HAS READ AND IS FAMILIAR WITH THE APPLICABLE SOILS
<br />REPORT.
<br />CONTRACTOR SHALL BE RESPONSIBLE FOR STRICTLY ADHERING TO THE RECOMMENDATIONS OF SAID
<br />SOILS REPORT FOLLOWING ALL APPLICABLE PROCEDURES NOTED THEREIN. EXISTING WATER TABLE SHALL
<br />POSSIBLY DETERMINE A DIFFERENT UTILIZATION OF THE TANK STRAPS AND TYPE OF BACK FILL
<br />MATERIAL. SHOULD GROUND WATER OR CONTAMINATION BE DISCOVERED DURING TANK EXCAVATION,
<br />WORK SHALL BE SUSPENDED PENDING REVIEW BY 7 -ELEVEN CONSTRUCTION MANAGER.
<br />4.4 CONTRACTOR SHALL REPORT ANY OBJECTION TO MATERIALS, APPLIANCES, OR METHODS OF
<br />CONSTRUCTION SHOWN OR SPECIFIED TO THE OWNER'S CONSTRUCTION MANAGER AND OBTAIN A
<br />DECISION BEFORE PROCEEDING.
<br />4.5 PROPOSALS: CONTRACTOR SHALL SUBMIT BID ONLY ON 7 -ELEVEN'S FORM THAT WILL BE PROVIDED BY
<br />7 -ELEVEN'S LOCAL CONSTRUCTION MANAGER, "COST OF CONSTRUCTION" PROPOSALS SUBMITTED ON ANY
<br />OTHER FORM SHALL BE REJECTED AND RETURNED. PROPOSALS NOT COMPLETELY AND PROPERLY FILLED
<br />OUT SHALL BE REJECTED. PROPOSALS SHALL INCLUDE MONEYS FOR REMOVAL OF ALL EXISTING
<br />IMPROVEMENTS AS REQUIRED FOR GASOLINE INSTALLATION.
<br />4.6 PERMITS: CONTRACTOR SHALL, AS DIRECTED BY 7 -ELEVEN, PAY FOR ALL APPLICABLE PERMITS AND AND FEES. COPIES OF
<br />PERMITS AND CERTIFICATES SHALL BE FORWARDED TO LOCAL 7 -ELEVEN CONSTRUCTION MANAGER'S OFFICE OR SITE
<br />MANAGER PRIOR TO COMMENCEMENT OF WORK. FINAL CERTIFICATION OF ACCEPTANCE BY GOVERNING AUTHORITIES
<br />SHALL ALSO BE ON FILE WITH LOCAL CONSTRUCTION OFFICE OR SITE MANAGER PRIOR TO THE PROCESSING OF FINAL
<br />PAYMENT REQUEST.
<br />4.7 INSPECTIONS: CONTRACTOR SHALL BE REQUIRED TO ADHERE TO ALL REQUIREMENTS OF OWNER'S INSPECTION
<br />PROGRAM. CONTRACTOR SHALL COMPLY WITH REQUIREMENTS FOR NOTIFICATION, SITE PREPARATION REQUIREMENTS,
<br />COMPLIANCE, ON-SITE PRESENCE DURING INSPECTION AND CORRECTION OF ANY DEFECTS OR RELATED PROBLEMS AS
<br />DIRECTED BY INSPECTING REPRESENTATIVE CONTRACTOR SHALL PROVIDE NO LESS THAN 48 HOURS NOTICE PRIOR TO
<br />INSPECTION.
<br />4.8 COORDINATION: FUEL CONTRACTOR SHALL BE RESPONSIBLE FOR SCHEDULING ALL PHASES OF THE GASOLINE
<br />INSTALLATION WITH THE GENERAL CONTRACTOR IN CHARGE OF THE BUILDING OR MAJOR PORTION OF THE PROJECT. THE
<br />BUILDING GENERAL CONTRACTOR AND THE FUEL CONTRACTOR SHALL JOINTLY DEVELOP A MUTUALLY AGREEABLE
<br />SCHEDULE AND TIMETABLE FOR COMPLETION ON THE GASOLINE INSTALLATION. TIMETABLE FOR BUILDING AND GASOLINE
<br />SHALL COINCIDE AND COMPLIMENT EACH OTHER SO THAT ONE DOES NOT DELAY THE OTHER.
<br />SHOULD FUEL CONTRACTOR FAIL TO MEET DEADLINES AS ESTABLISHED BY THE SCHEDULE AND/OR HOLD UP THE
<br />COMPLETION OF THE OVERALL BUILDING PROJECT, 7 -ELEVEN, INC. RESERVES THE RIGHT TO RECTIFY THE SITUATION
<br />ACCORDINGLY.
<br />4.9 CONTRACTOR SHALL PROVIDE OWNER WRITTEN CERTIFICATION AS TO THE FOLLOWING:
<br />4.9.1 CERTIFICATION FROM LOCAUSTATE GOVERNING AUTHORITIES AS APPLICABLE FOR CONTRACTOR
<br />CERTIFICATION/LICENSING FOR INSTALLATION OF GASOLINE STORAGE TANK SYSTEM.
<br />4.9.2 CERTIFICATION FROM EQUIPMENT MANUFACTURES AND SUPPLIERS (TANKS, PRODUCT LINES,
<br />ATG'S, ETC.) AS TO ATTENDING AND ACHIEVING CERTIFICATION FROM APPROPRIATE COMPANY FOR
<br />INSTALLATION OF EQUIPMENT.
<br />4.9.3 CERTIFICATION ON APPROPRIATE FORMAT AS TO INSTALLATION OF COMPLETE SYSTEM BEING
<br />PERFORMED IN COMPLIANCE WITH ALL LOCAL, STATE AND FEDERAL LAWS AND REGULATIONS.
<br />4.9.4 CERTIFICATION THAT ALL EQUIPMENT EITHER SUPPLIED BY OWNER OR CONTRACTOR HAS BEEN
<br />INSTALLED AS PER MANUFACTURER'S SPECIFICATIONS BY PERSONNEL TRAINED AND QUALIFIED
<br />FOR THAT SPECIFIC ITEM.
<br />SECTION I GENERAL CONDITIONS - CONTINUED
<br />PART 4 - CONTINUED
<br />4.11 LIENS: CONTRACTOR SHALL PERMIT NO LIENS OF ANY KIND TO BE FIXED UPON OR AGAINST THE PROPERTY BY ITS
<br />SUBCONTRACTORS, LABORERS, MECHANICS OR MATERIAL MEN, AND SHALL INDEMNIFY, PROTECT AND SAVE OWNER
<br />HARMLESS FROM AND AGAINST ALL SUCH CLAIMS AND LIENS.
<br />4.12 EQUIPMENT RESPONSIBILITY: CONTRACTOR SHALL BE RESPONSIBLE FOR SCHEDULING, RECEIVING, UNLOADING,
<br />HANDLING AND PROVIDING PROTECTED INSIDE STORAGE FOR ALL OWNER SUPPLIED EQUIPMENT AND MATERIAL.
<br />CONTRACTOR SHALL INSPECT EQUIPMENT UPON RECEIPT AND IMMEDIATELY REPORT ANY DAMAGE DUE TO SHIPPING TO
<br />THE OWNER'S REPRESENTATIVE. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE DUE TO FAILURE TO COMPLY
<br />WITH THESE REQUIREMENTS. DISPENSERS SHALL BE PROTECTED WITH SHIPPING BOXES UNTIL STORE IS TURNED OVER
<br />FOR OPENING. CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR ADEQUATE AND LOCKED STORAGE OF OWNER'S
<br />MISCELLANEOUS EQUIPMENT, TO INCLUDE GASOLINE CONSOLE, PRIOR TO OPENING OF THE STORE.
<br />4.13 FUEL CONTRACTOR SHALL BE RESPONSIBLE FOR FILING OF RECEIVING FORMS AND MISCELLANEOUS CONFIRMATION OF
<br />EQUIPMENT RECEIVING INFORMATION AS REQUIRED BY LOCAL CONSTRUCTION OFFICE.
<br />4.14 FUEL CONTRACTOR SHALL PROVIDE ALL PIPING, WIRING, MATERIAL AND LABOR AS REQUIRED TO INSTALL OWNER
<br />SUPPLIED EQUIPMENT. INCLUDE MONEY IN BID PROPOSAL FOR INSTALLATION OF OWNER SUPPLIED EQUIPMENT UNLESS
<br />NOTED OTHERWISE.
<br />PART 5 - PROTECTION
<br />5.1 CONTRACTOR SHALL BE HELD RESPONSIBLE FOR ANY LOSS OR DAMAGE CAUSED BY HIM OR HIS WORKMEN TO THE
<br />PROPERTY OR EQUIPMENT OF THE OWNER, OR TO THE WORK OR MATERIALS OF OTHER CONTRACTORS. CONTRACTOR
<br />SHALL MAKE GOOD ANY LOSS, DAMAGE OR INJURY WITHOUT COST TO OWNER FOR SUCH LOSS OR DAMAGE.
<br />5.2 CONTRACTOR SHALL PROVIDE AND MAINTAIN SUITABLE TEMPORARY SIDEWALKS FENCES LIGHTS SIGNS OR OTHER
<br />STRUCTURES AND DEVICES AS REQUIRED BY LAW, DO NOT OBSTRUCT OR INTERFERE WITH TRAFFIC IN PUBLIC STREETS,
<br />ALLEYWAYS OR PRIVATE RIGHT-OF-WAYS. IF WORK IS SUSPENDED, KEEP ALL ROADWAYS AND SIDEWALKS IN PROPER
<br />CONDITION AND PUT AND LEAVE THEM IN PROPER CONDITION AT TERMINATION OF WORK.
<br />5.3 CONTRACTOR SHALL SEND PROPER NOTICES, MAKE NECESSARY ARRANGEMENTS AND PERFORM ALL WORK REQUIRED
<br />FOR THE CARE, PROTECTION AND MAINTENANCE OF PUBLIC UTILITIES ON AND AROUND THE BUILDING SITE, ASSUMING ALL
<br />RESPONSIBILITY AND PAYING ALL COSTS FOR WHICH THE OWNER MAY BE LIABLE. CONTRACTOR HEREBY DECLARES HE
<br />HAS VERIFIED THE LOCATIONS OF THE EXISTING UNDERGROUND UTILITIES ON SITE PRIOR TO THE START OF WORK.
<br />CONTRACTOR HEREBY AGREES TO MAKE ARRANGEMENTS FOR AND TO PAY ALL CHARGES IN CON- JUNCTION WITH THE
<br />RELOCATION'S OF EXISTING UTILITIES AS REQUIRED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY AND ALL UTILITY
<br />EASEMENTS, HOOKUP CHARGES, TAP FEES & SYSTEM DEVELOPMENT FEES OR BONDS AS NECESSARY FOR COMPLETION
<br />OF THIS PROJECT.
<br />5.4 IF ALL OR PART OF THE WORK IS SUSPENDED FOR ANY REASON, CONTRACTOR SHALL PROPERLY COVER OVER, SECURE
<br />AND PROTECT ANY PORTION LIABLE TO SUSTAIN INJURY FROM ANY CAUSE.
<br />5.5 PRODUCT PROTECTION: CONTRACTOR SHALL PROVIDE ADEQUATE AND SECURE PROTECTION OF PRODUCT IN TANKS
<br />UPON DELIVERY UNTIL TURNED OVER FOR OPERATION. ALL FILL, VENT AND GAUGING CAPS AND/OR OPENINGS SHALL BE
<br />SECURED AND PADLOCKED TO PREVENT VANDALISM OR THEFT.
<br />PART 6 - SUBSTITUTION OF MATERIALS
<br />6.1 MATERIALS AS SPECIFIED REPRESENT REQUIRED STANDARDS. SUBSTITUTION MAYBE PROPOSED IN WRITING WITH
<br />ADEQUATE SUPPORTING DATA FURNISHED. USE OF SUBSTITUTE MATERIALS IS DEPENDENT ON RECEIPT OF WRITTEN
<br />APPROVAL FROM OWNER'S APPROVED REPRESENTATIVE.
<br />PART 7 - COMPLETION OF CONTRACT
<br />7.1 THE CONTRACT SHALL BE CONSIDERED FULFILLED, SAVE AS PROVIDED IN ANY MAINTENANCE STIPULATIONS, BOND OR BY
<br />LAW, WHEN ALL THE WORK HAS BEEN COMPLETED WITH FINAL INSPECTION AND ACCEPTANCE MADE BY ALL APPLICABLE
<br />GOVERNING BUILDING DEPARTMENTS, FIRE MARSHAL'S OR OTHER JURISDICTIONS.
<br />7.2 NOT USED
<br />7.3 CLEANING:
<br />7.3.1 ALL WORK SHALL BE CLEAN AND READY FOR USE UPON COMPLETION. REMOVE TEMPORARY TAPES,
<br />WRAPPING COATING PAPER LABELS AND OTHER ITEMS.
<br />7.3.2 CLEANING METHODS FOR PROPRIETARY MATERIALS SHALL BE IN STRICT ACCORDANCE WITH
<br />MANUFACTURER'S INSTRUCTIONS. CLEANING SOLUTIONS, AGENTS, SOLVENTS, WAXES OR OTHER
<br />MATERIALS SHALL BE ONLY AS APPROVED BY THE MANUFACTURER OF THE MATERIAL INSTALLED IN
<br />THE WORK.
<br />7.3.3 CLEANUP: CONTRACTOR SHALL CLEAN UP ALL DEBRIS CAUSED BY THE WORK OF THIS SECTION,
<br />KEEPING THE PREMISES NEAT AT ALL TIMES.
<br />PART 8 - CODES
<br />8.1 THE FOLLOWING CODES ARE MADE APART OF THIS SPECIFICATION. SAID CODES SHALL DICTATE MINIMAL ACCEPTABLE
<br />STANDARDS. CODE SHALL BE ADHERED TO UNLESS LOCAL GOVERNING AUTHORITIES DICTATE HIGHER OR MORE
<br />STRINGENT REQUIREMENTS WHICH SHALL TAKE PRECEDENCE:
<br />8.1.1 NFPA 30 FLAMMABLE AND COMBUSTIBLE LIQUIDS CODE
<br />8.1.2 PEI MANUAL "RECOMMENDED PRACTICES FOR INSTALLATION OF UNDERGROUND LIQUID STORAGE
<br />SYSTEMS." #RP -100-96 (OR LATEST EDITION)
<br />8.1.3 OSHA AND LOCAL MUNICIPALITIES
<br />PART 9 - WARRANTY / GUARANTEE
<br />9.1 EXCEPT WHERE SPECIAL GUARANTEES ARE REQUIRED IN EXCESS OF ONE (1) YEAR, THE CONTRACTOR AGREES TO REPAIR
<br />AND RE -CERTIFY OR REPLACE THE DEFECTIVE COMPONENT OR ANY DEFECT IN MATERIAL OR WORKMANSHIP (BEYOND
<br />ORDINARY WEAR AND TEAR) TO THE SATISFACTION OF THE OWNER'S CONSTRUCTION MANAGER FOR A PERIOD OF ONE (1)
<br />YEAR AFTER DATE OF ACCEPTANCE, WHETHER IN HIS WORK OR IN THAT OF SUBCONTRACTOR'S, WITHOUT COST TO THE
<br />OWNER.
<br />9.2 ALL PAVING WILL HAVE A TWO YEAR WARRANTY.
<br />PART 10 - AS BUILT PLAN AND DOCUMENTATION
<br />10.1 UPON COMPLETION OF PROJECT, CONTRACTOR SHALL PROVIDE "AS -BUILT SITE PLAN" VERIFYING FINAL LOCATION OF
<br />IMPROVEMENTS INCLUDING, BUT NOT LIMITED TO, PIPING, PLUMBING AND ELECTRICAL.
<br />10.2 CONTRACTOR SHALL KEEP PHOTOGRAPHIC JOURNAL OF ALL PHASES OF THE COMPLETE INSTALLATION. PHOTOGRAPHS
<br />ARE TO BE PROPERLY DATED, IDENTIFIED AND FORWARDED TO LOCAL 7 -ELEVEN, INC. CONSTRUCTION OFFICE, WITH FINAL
<br />INVOICE PACKAGE.
<br />SECTION II INSPECTIONS / TESTING
<br />TEST BEFORE PLACING THE SYSTEM IN SERVICE
<br />COMPONENT
<br />MANUFACTURER
<br />Table below lists current Manufacturer's Installation and Testing Guidelines that may
<br />be applied to the fuel system components after assembly but before backfilling.
<br />Before the beginning of fuel system installation, fuel contractor is to be responsible
<br />for reading through the entire Installation Manual and Operating Guidelines as well as
<br />any applicable supplemental materials. It is the responsibility of the fuel contractor
<br />and fuel operator to understand and follow all requirements contained in the
<br />installation and testing manuals. Work must be performed according to standard
<br />industry practices applicable to tank installations and operations. Work must also
<br />comply will all applicable codes, regulations and standards of appropriate
<br />governmental agencies.
<br />DOUBLE -WALLED STORAGE
<br />TANK
<br />XERXES"A ZCL
<br />COMPANY"
<br />INSTALLATION
<br />MANUAL
<br />http://www.zcl.com/assets/documents/library/installation%20
<br />manual%20and%20operating%20guidelines%20(imog)%20for%
<br />20xerxes%20tanks.pdf
<br />TESTING
<br />PROCEDURE
<br />http://www.zcl.com/assets/documents/library/installation%20
<br />manual%20and%20operating%20guidelines%20(imog)%20for%
<br />20xerxes%20tanks.pdf
<br />DOUBLE -WALLED PIPING
<br />NOV
<br />INSTALLATION
<br />MANUAL
<br />http://www.nm.com/Segments/Completion_ and_Production_
<br />Solutions/Fiber _Glass _Systems/Fuel_Handling/Red_Thread_IIA.
<br />aspx
<br />TESTING
<br />PROCEDURE
<br />http://www.nov.com/docHandler.aspx?puld=12bNZwjC3oL35C
<br />LEAK DETECTION SENSOR
<br />VEEDER ROOT
<br />INSTALLATION
<br />MANUAL
<br />http://www.gilbarco.com/gold/gold_public_access.cfm?section
<br />id`361
<br />TESTING
<br />PROCEDURE
<br />http://www.gilbarco.com/gold/gold_public_access.cfm?section
<br />_id=361
<br />AUTOMATIC TANK GUAGES
<br />VEEDER ROOT
<br />INSTALLATION
<br />MANUAL
<br />http://www.gilbarco.com/gold/gold_public_access.cfm?section
<br />id=364
<br />TESTING
<br />PROCEDURE
<br />http://www.veeder.com/us/products/tls-automatic-tank-gauge
<br />-systems/atg-tis-consoles/tls-350r-automatic-tank-gauge
<br />OVERFILL PREVENTION DEVICES
<br />OPW
<br />INSTALLATION
<br />MANUAL
<br />http://www.opwglobal.com/docs/libraries/manuals/retail-fuel;
<br />ng/below-ground/opw-fcs-manuals/71so-testable-(h1S524pa)-
<br />1-30-14.pdf?sfvrsn=4
<br />TESTING
<br />PROCEDURE
<br />http://www.opwglobal.com/docs/libraries/manuals/retail-fuell
<br />ng/below-ground/opw-fcs-manuals/71so-testable-(h15524pa)-
<br />1-30-14.pdf?sfvrsn=4
<br />SPILL -CONTAIN MENTOPW
<br />MANHOLES
<br />INSTALLATION
<br />MANUAL
<br />http://www.opwgloba Isom/docs/libra ries/ma nua Is/retai I -fuel i
<br />ng/below-ground/opw-fcs-manuals/1-3100_ EDGE_ Thread -On_
<br />Spill_lnstallation_Inst_202181_2-13-13_G.pdf7Status=Master&
<br />sfvrsn=0
<br />TESTING
<br />PROCEDURE
<br />http://www.opwgloba I som/docs/libraries/ma nua Is/Teta; I -fuel i
<br />ng/below-ground/opw-fcs-ma nua Is/Double_W all_Spill Contain
<br />er_Vac _Test _Installation _Instructions- _English_202383.pdf?St
<br />atus=Master&sfvrsn=0
<br />IMPACT VALVES
<br />OPWat-Master&sf-r
<br />INSTALLATION
<br />MANUAL
<br />es/manuals/retal-fue
<br />http://www.opwglobal.com/docs/librariili
<br />ng/below-ground/opw-fcs-ma nua Is/10_Series_Emergency_She
<br />ar_Valve _Installation_Instructions=_English_H31374PA.pdf?St
<br />0
<br />TESTING
<br />PROCEDURE
<br />http://www.opwglobal.com/docs/libraries/manuals/retall-fuell
<br />ng/below-ground/opw-fcs-manuals/10_Series _Emergency_She
<br />ar_Valve _Installation _Instructions _-_English_ H31374PA.pdf?St
<br />atus=Master&sfvrsn=0
<br />LINE LEAK
<br />DETECTORS
<br />VAPORLESS
<br />MANUFACTURING
<br />INSTALLATION
<br />MANUAL
<br />http://www.vaporless.com/installation/installpdf/install_ld200
<br />0Pdf
<br />0Pdf
<br />TESTING
<br />PROCEDURE
<br />htt: www.va orless.com installation install df install_Id200
<br />P// P / / P /
<br />O.pdf
<br />ELECTRONIC LINE LEAK
<br />DETECTORS
<br />VEEDER ROOT
<br />INSTALLATION
<br />MANUAL
<br />http://www.veeder.com/gold/download.cfm?doc_id=6414
<br />TESTING
<br />PROCEDURE
<br />http://www.veeder.com/gold/download.cfm?doc_id=6414
<br />FLEXIBLE CONNECTORS
<br />FRANKLIN
<br />FUELING
<br />INSTALLATION
<br />MANUAL
<br />http://www.franklinfueling.com/media/468560/407293001-r1-
<br />flex-connector-install.pdf
<br />PART 1 - GENERAL
<br />1.1 SCOPE: THIS SECTION COVERS THE FURNISHING OF ALL LABOR, SERVICES AND EQUIPMENT AS REQUIRED TO PROVIDE
<br />INSPECTION SERVICES OF THE FUELING INSTALLATION.
<br />PART 2 - INSPECTIONS
<br />2.1 INSPECTOR: 7 -ELEVEN, INC. LOCAL CONSTRUCTION DEPARTMENT AND/OR APPOINTED REPRESENTATIVE SHOULD BE
<br />NOTIFIED TO OBSERVE TIGHTNESS TESTING OF PRODUCT PIPING, STAGE I & STAGE II PIPING PRIOR TO BACKFILL.
<br />2.2 NOTIFICATION: CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING 7 -ELEVEN'S CONSTRUCTION DEPARTMENT 48
<br />HOURS PRIOR TO REQUESTED INSPECTION
<br />2.3 SPILLAGE: SHOULD SPILLAGE OF PRODUCT OCCUR AT ANY PHASE OF INSTALLATION OR TESTING, LOCAL 7 -ELEVEN
<br />CONSTRUCTION DEPARTMENT AND ENVIRONMENTAL DEPARTMENT ARE TO BE NOTIFIED IMMEDIATELY, ESTIMATED LOSS
<br />OFPRODUCT AS WELL AS ACTION TO BE TAKEN BY CONTRACTOR TO SAFEGUARD THE EVENT FROM FURTHER MISHAP AND
<br />TO PROTECT THE GENERAL PUBLIC IS TO BE NOTED AND RECORDED.
<br />2.4 REPRESENTATIVE OF CONTRACTOR AND FUEL CONTRACTOR SHALL BE AVAILABLE ON SITE DURING TESTING PROGRAMS.
<br />FAILURE TO COMPLY WITH THIS REQUIREMENT WILL RESULT IN ANY CORRECTIONS AND/OR REPAIRS REQUIRED BEING
<br />PERFORMED BY OWNER AS REQUIRED. COST OF SAID REPAIRS AND/OR CONNECTIONS SHALL BE DEDUCTED FROM
<br />CONTRACT AMOUNT AS REQUIRED TO SATISFY THE SITUATION.
<br />2.5 PROHIBITED WORK: CONTRACTOR SHALL SCHEDULE WORK SUCH THAT NO HEAVY EQUIPMENT IS OPERATING ON SITE
<br />DURING INSPECTION PROGRAMS. NO WELDING OR OPEN FLAMES SHALL BE ALLOWED ON SITE AT ANY TIME DURING TEST
<br />PROCEDURES.
<br />2.6 INSTALLATION REPORTS: SHOULD 7 -ELEVEN OR THEIR APPOINTED REPRESENTATIVES BE UNABLE TO BE PRESENT AT SITE
<br />FOR PURPOSES OF FILING ANY INSPECTION REPORTS, CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLETE INSPECTION
<br />AND FILING OF REPORT WITH LOCAL 7 -ELEVEN, INC. CONSTRUCTION OFFICE. WRITTEN REPORT SHALL INCLUDE
<br />PHOTOGRAPHIC DOCUMENTATION OF ALL PROCEDURES.
<br />2.7 TEST FAILURE: SHOULD SYSTEM FAIL ANY PORTION OF TEST PROGRAM, CONTRACTOR SHALL IMMEDIATELY INSTIGATE
<br />PROCEDURES AS REQUIRED TO BRING SYSTEM INTO COMPLIANCE SHOULD FAILURE OF TEST DUE TO FACILITY WORK
<br />REQUIRE EXPENDITURE OF ADDITIONAL MONIES FOR RESCHEDULING AND/OR RETESTING OF SYSTEM, CONTRACTOR
<br />SHALL BE HELD RESPONSIBLE FOR COMPENSATION ACCORDINGLY.
<br />2.8 CLEANUP: IN THE EVENT PRODUCT SPILLAGE SHOULD OCCUR DURING CONSTRUCTION OR DURING WARRANTY PERIOD
<br />DUE TO WORK PERFORMED BY CONTRACTOR, CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANUP AS MAY BE REQUIRED.
<br />2.9 TEST REPORT: UPON COMPLETION OF TESTING PROGRAMS, REPRESENTATIVE OF TESTING/ INSPECTION COMPANY SHALL
<br />BE RESPONSIBLE FOR FILING COPIES OF TANK AND PIPING TEST/INSPECTION REPORTS WITH LOCAL 7 -ELEVEN, INC.
<br />CONSTRUCTION OFFICE OR THE OWNER'S ASSIGNED SITE MANAGER WITH COPY TO JOB SITE.
<br />I Proto 11-05-18 1
<br />M
<br />0
<br />QQXN
<br />' W �
<br />U�
<br />Z Z �3uNi
<br />rn
<br />z
<br />Z� OU
<br />W Z2z
<br />W >Z�
<br />Wit Jho
<br />ti Wm t Wim
<br />U �
<br />Q
<br />2
<br />0
<br />M
<br />10
<br />Z
<br />Q
<br />U
<br />U
<br />W
<br />a
<br />V1
<br />c�
<br />Z
<br />W
<br />0
<br />LL
<br />35558
<br />G13.0
<br />FUELING - USA
<br />
|