Timeline <br /> Extension of Closure Cap <br /> Corral Hollow Sanitary Landfill <br /> Rev April 8,2008 <br /> Activity Duration Total Completion Note <br /> (Weeks) (Weeks) Date <br /> Start 0 0 8-Jan-08 <br /> Agreement on closure approach with CalTrans 0 0 8-Jan-08 CalTrans chooses not to participate <br /> Conceptual design for closure --4 4 5-Feb-08 <br /> Review and comment by regulatory agencies 3 7 26-Feb-08 <br /> Incorporation of comments, and the 6 13 8-Apr-08 Submitted 1-Apr-08 <br /> preparation of amendment to Closure Plan <br /> and postclosure maintenance plan ---- <br /> Review of CP/PCMC by regulatory agencies 17 34.3 4-Sep-08 120 days per Title 27_ <br /> Incorporation of agency review comments 3 37.3 25-Sep-08 Depends on comments received <br /> Review of revisions by regulatory agencies 3 40.3 16-Oct-08 Duration uncertain <br /> Preparation of construction documents 4 44.3 13-Nov-08 by County staff <br /> and CQA Manual by consultant? <br /> Review of construction documents by regulatory agencies 3 47.3 4-Dec-08 optimistic <br /> Incorporation of regulatory agency comments 2 49.3 18-Dec-08 Depends on comments received <br /> Review of bid package by Pub Works Design Division 2 51.3 1-Jan-09 <br /> Incorporation of Design Division comments 2 53.3 15-Jan-09 <br /> Preparation of bid package, place on BOS agenda 3 56.3 5-Feb-09 <br /> Bid period 4 60.3 5-Mar-09 <br /> Resolution of contract issues, NTP 4 64.3 2-Apr-09 <br /> Construction 8 72.3 28-May-09 Construction complete <br /> Project assumptions: <br /> 1 Design by Public Works'Staff <br /> J <br /> 2 CQA Plan and CQA can be by firms with professional service.agreements in place(Vector Engr). No additional time <br /> will be needed for these contractual arragements. <br /> N:\1 Corral Hollow\ClosureCover\CloCapExtn\Ext of Closure Cap Project-08\CH-CloCap Ext PI-Calndr-Timeline.xls Printed 8/25/2008 <br />