JSA 15: GROUNDWATER EXTRACTION AND/OR SVE SYSTEM INSTALLATION <br /> <br />March 30, 2010 <br />Field staff must review job-specific work plan and coordinate with project manager to verify that all up-front logistics are completed prior to starting work including, but not limited to, <br />permitting, access agreements, and notification to required contacts (e.g. site managers, inspectors, clients, subcontractors, etc.). A tailgate safety meeting must be performed and <br />documented at the be•innin. <br />0 Job Steps <br />of each work da . Weather conditions heat, <br />0 Personal Protective Equipment <br />cold, rain, li.htnint must also be <br />0 Potential Hazard <br />considered. <br />0 Critical Actions <br />Mobilize with proper <br />equipment/supplies for <br />trenching. <br />Gather necessary PPE. Reflective vest for <br />traffic, steel toed and shank shoes, hard <br />hat, safety glasses with side shields, ear <br />plugs/muffs, leather gloves for the non- <br />chemical aspects of work as necessary; <br />Wear an appropriate air purifying respirator <br />with combination organic vapor/HEPA <br />P-100 cartridges, and other PPE as <br />needed. (Use a North respirator or its <br />equivalent. Best brand nitrile gloves or <br />their equivalent. Foam earplugs with an <br />NRR of 33. Tyvek, poly coated chemical <br />resistant suit or its equivalent). <br />Traffic hazards. <br />Vehicle accident. <br />Lifting hazards. <br />Delay or improper performance <br />of work due to improper <br />equipment on site. <br />Start project with a Daily Health and Safety Briefing. <br />Follow safe driving procedures. <br />Employ safe lifting procedures. <br />Make sure sub-contractors are aware of their responsibilities for labor, <br />equipment and supplies. <br />Review permit conditions. <br />Develop a traffic control plan with the client and/or local agencies as <br />applicable. Plan may include use of cones, barrier tape, jersey <br />barriers, etc. (Include in site-specific HASP). <br />It is the responsibility of the SHSO to annotate the Site Plan with <br />the Traffic Control configuration if an Approved Traffic Control <br />Plan is not available. <br />Visually clear the <br />proposed trenching and <br />above-ground structure <br />locations. Mark out the <br />proposed trenching <br />locations. <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Traffic hazards. <br />Overhead and underground <br />lines & installations, <br />Electrocution, explosion, product <br />release, property damage, <br />interruption of services. <br />Review proposed location map in advance of arriving on site. <br />Complete Pre-Mobilization section of Utility Clearance Review form <br />and adjust drilling locations as necessary. <br />Coordinate with Station Manger (or designee) to minimize potential <br />conflicts. <br />Set up necessary traffic <br />control, if necessary. See <br />site-specific HASP for <br />detailed plan if available. <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Struck by vehicle during <br />placement. <br />Vehicle accident as a result of <br />improper traffic control <br />equipment placement. <br />Use buddy system for placing traffic control. <br />Implement traffic control plan such as setting out cones and tape <br />defining safety area. <br />Adhere to approved Traffic Control Plans when working in roadways. <br />(See site-specific HASP). <br />It is the responsibility of the SHSO to annotate the Site Plan with <br />the Traffic Control configuration if an Approved Traffic Control <br />Plan is not available. <br />Set up exclusion zone(s). Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Struck by vehicle during set up. <br />Slip/fall hazards. <br />Implement exclusion zone. <br />It is the responsibility of the SHSO to annotate the Site Plan with <br />the Exclusion Zone set-up. <br />Set up workstations with clear walking paths to and from trenching. <br />Use safety tape and cones. <br />Cut pavement. Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety_glasses <br />Traffic hazard. Identify and barricade work area. <br />Paper copies are uncontrolled and are valid only at the time of printing. The electronic version may he downloaded from SGI's intranet. <br />Page 1 of 4 <br /> The Source Group, Inc.