JSA 15: GROUNDWATER EXTRACTION AND/OR SVE SYSTEM INSTALLATION <br /> <br />March 30, 2010 <br />Field staff must review job-specific work plan and coordinate with project manager to verify that all up-front logistics are completed prior to starting work including, but not limited to, <br />permitting, access agreements, and notification to required contacts (e.g. site managers, inspectors, clients, subcontractors, etc.). A tailgate safety meeting must be performed and <br />documented at the be.innin. <br />0 Job Steps <br />of each work da . Weather conditions heat, <br />0 Personal Protective Equipment <br />cold, rain, li.htnin. must also be <br />0 Potential Hazard <br />considered. <br />0 Critical Actions <br />Exposure to chemical hazards. Monitor air quality in accordance with the site-specific Health and <br />Safety Plan. <br />Have appropriate respirator with combination organic vapor/HEPA P- <br />100 cartrids within 3-5 feet of work area, readily available. <br />Pressure-test piping <br />(primary and secondary <br />conduit as required). <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Eye injury. Don't over pressurize piping (usually <10 psi). Verify security of end <br />caps. <br />Install electrical line and <br />conduit to well heads. <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Collapse of trench on workers. <br />Vehicle or foot traffic. <br />Falling into open trench. <br />Trip hazards. <br />Lifting hazard. <br />-- <br />Use shoring/benching/sloping of trench walls or trench boxes if <br />workers will have head and shoulders below top of trench (always for <br />>5 ft deep, but may be required for <5 feet as well). <br />Maintain adequate access/egress locations for workers in trench. <br />Keep trench covered in non-active work areas and between work <br />shifts. <br />• Use proper lifting techniques. <br />Keep work area clean, minimizina slip, trip and fall hazards.. _ <br />Backfill and pave trench. Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Injury from heavy equipment. <br />Leg or foot injury from <br />compaction equipment. <br />Future accidents or damage as <br />a result of subsidence. <br />Traffic hazards. <br />Maintain eye contact with equipment operators. <br />Use agreed-upon hand signals. <br />Wear proper PPE during compaction. <br />Perform compaction of backfill in accordance with specifications. <br />Construct treatment <br />equipment pad. <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Damage from heavy equipment. <br />Trip hazard on rebar. <br />Body position / lifting hazard. <br />Traffic hazards. <br />Use agreed-upon hand signals with truck operator. <br />Keep work area free of debris and supplies orderly. <br />Place and attach major <br />equipment components. <br />(Utilize Crane JSA as <br />applicable). <br />Wear reflective vest for traffic, steel toed <br />and shank shoes, hardhat, safety glasses <br />with side shields, and leather gloves as <br />necessary. <br />Injury from transport equipment. <br />Back strain when moving <br />equipment. <br />Eye or hand injury when using <br />power tools. <br />Keep clear of equipment when large components are being set in <br />place. <br />Use mechanical assistance as needed to arrange equipment into <br />place. <br />Wear proper PPE when bolting equipment to pad. <br />Paper copies are uncontrolled and are valid only at the time of printing. The electronic version may be downloaded from SGIs intranet. <br />Page 3 of 4 <br /> The Source Group, Inc.