TANK AND PIPING INSTALLATION SCOPE OF WORK:
<br />GENERAL:
<br />SCOPE OF WORK: UNLESS SPECIFIED OTHERWISE ON THESE DRAWINGS, THE GENERAL CONTRACTOR SHALL FURNISH ALL WORK AND MATERIALS TO
<br />COMPLETE THE INSTALLATION OF THE SYSTEMS AND EQUIPMENT SHOWN IN THESE DRAWINGS AND AS REQUIRED BY PROJECT DOCUMENTS PROVIDED
<br />TO THE CONTRACTOR.
<br />WHERE THESE DRAWINGS DIFFER FROM LOCAL REGULATIONS, LOCAL REGULATIONS WILL SUPERSEDE THESE DRAWINGS IF THEY ARE MORE STRINGENT.
<br />NOTE:
<br />THESE GUIDELINES APPLY ONLY TO UNDERGROUND STORAGE TANKS AND PRODUCT PIPING. REFER TO BALANCE OF SITE SPECIFIC DOCUMENTS/
<br />DRAWINGS FOR SPECIFICATIONS REGARDING CONCRETE/ASPHALT INSTALLATION, ELECTRICAL REQUIREMENTS, AND SANITARY & STORM SEWERS
<br />INSTALLATION.
<br />*** WHERE MULTIPLE VERSIONS OF THE SAME SHEET EXIST, INSERT ***
<br />THE SHEET APPROPRIATE FOR THE SPECIFIC STATION LAYOUT.
<br />ARCHITECTURAL AND CIVIL DRAWINGS SHALL TAKE PRECEDENCE FOR REFERENCING ALL DIMENSIONS, PROPERTY LINES, ELEVATIONS AND
<br />EQUIPMENT LOCATIONS
<br />ALL DIMENSIONS AND CONDITIONS SHALL BE CHECKED AND VERIFIED IN THE FIELD BEFORE STARTING ANY WORK. ANY DISCREPANCY SHALL
<br />BE CALLED TO THE ATTENTION OF THE OWNERS ENGINEER FOR HIS DECISION BEFORE PROCEEDING WITH THE WORK.
<br />ALL REQUESTS TO ADD, DELETE, OR SUBSTITUTE MATERIAL AND EQUIPMENT SHOWN ON THESE DRAWINGS MUST BE REVIEWED AND APPROVED BY
<br />THE OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER, IN CHARGE OF THE PROJECT. ALL CHANGES MUST BE REVIEWED WITH
<br />THE MARKETING FUELS MANAGER.
<br />THE CONTRACTOR IS REQUIRED TO FURNISH AS -BUILT DRAWINGS TO LOCATE TANKS AND PIPING AS INSTALLED AFTER THE COMPLETION OF THE
<br />PROJECT.
<br />(1) TANK INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL DOUBLE WALL FIBERGLASS TANKS WITH COMPLETE "VEEDER ROOT -TLS -350 PLUS" TANK AND PIPING
<br />MONITORING AND ALARM SYSTEM. TANKS TO BE SET MIN. 60" BELOW FINISH GRADE. SEE SITE SPECIFIC INSTALLATION DETAILS FOR TANK SIZES AND
<br />LOCATIONS.
<br />NYC VARIANT: INSTALL TOP AND BOTTOM SLAB AND SLAB PIER SUPPORT SYSTEM PER NYC STANDARDS.
<br />TANK SIZING GUIDELINES:
<br />SPECIFIC BUSINESS UNIT TANK SIZE REQUIREMENTS ARE RECOMMENDED. TANK SIZING MODELS CAN BE RUN BY CONTACTING FUEL SYSTEM DESIGN
<br />MANAGER - AMERICAS.
<br />LOCATION OF TANKS AND ASSOCIATED EQUIPMENT ON PROPERTY: FINAL FACILITY EQUIPMENT LOCATIONS INCLUDING PLACEMENT AND
<br />ORIENTATION OF TANKS, EMERGENCY SHUTOFF SWITCHES, OVERFILL ALARMS (IF PRESENT) TO BE APPROVED BY BP DISTRIBUTION PRIOR
<br />TO SUBMITTAL FOR PERMITS TO ENSURE CLEAR AND SAFE ACCESS TO THE UNDERGROUND TANKS FOR UNLOADING OPERATIONS. THE
<br />GENERAL CONTRACTOR IS RESPONSIBLE FOR CONFIRMING APPROVED TANK AND EQUIPMENT LOCATIONS HAS BEEN DOCUMENTED W/ BP
<br />DISTRIBUTION, THE SITE ENGINEER AND/OR OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER PRIOR TO THE
<br />COMMENCEMENT OF WORK.
<br />TANKS:
<br />SHALL BE UNDERWRITERS LABORATORY APPROVED LISTED FOR THE UNDERGROUND STORAGE OF ALL FLAMMABLE AND COMBUSTIBLE MOTOR FUELS
<br />AS CALLED FOR ON THE SITE SPECIFIC DRAWING OR AS DESIGNATED ON THE SUPPLEMENTAL CONDITIONS AND SHALL BE DOUBLE WALL TANKS OF
<br />FIBERGLASS REINFORCED PLASTIC (FRP). INSTALLATION OF TANKS AND PIPING SHALL BE IN ACCORDANCE WITH U.L. LISTED MANUFACTURER'S
<br />INSTRUCTIONS. INSTALLATION SHALL CONFORM TO NFPA-30/30A AND ALL APPLICABLE LOCAL, STATE AND FEDERAL REGULATIONS. TANKS SHALL
<br />ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE STATE IN WHICH THE TANKS ARE TO BE INSTALLED AND BY THE TANK
<br />MANUFACTURER.
<br />THE UNDERGROUND STORAGE TANK SYSTEM SHALL BE COMPATIBLE WITH THE PRODUCT STORED. ALL CONTINUOUS MONITORING
<br />DEVICES SHALL BE INSTALLED PER MANUFACTURER'S SPECIFICATIONS.
<br />ALL MATERIALS USED IN THE INSTALLATION SHALL BE COMPATIBLE WITH USE FOR THE INTENDED PURPOSE AS PER NATIONALLY
<br />RECOGNIZED CODES, LOCAL CODES AND GOVERNING AUTHORITIES.
<br />METHANOL COMPATIBILITY: FOR ALL METHANOL COMPATIBLE STORAGE SYSTEMS, ALL READILY ACCESSIBLE COMPONENTS SHALL BE METHANOL
<br />COMPATIBLE FOR THE IMMEDIATE INTENDED SERVICE.
<br />BIO -DIESEL COMPATIBILITY: CURRENTLY AT THIS TIME, NO TANKS ARE LISTED FOR BIO -DIESEL SERVICE APPLICATIONS.
<br />INITIAL TANK TESTING:
<br />NEW TANKS SHALL BE INSPECTED UPON ARRIVAL AT SITE, AFTER UNLOADING FROM THE TRUCK, FOR VISUAL DAMAGE PRIOR TO INSTALLATION.
<br />- FOR DRY ANNULAR SPACE TANKS AIR/SOAP TESTS MUST BE PERFORMED AT THE JOB SITE PRIOR TO INSTALLATION TO VERIFY THE ABSENCE
<br />OF DAMAGE.
<br />- FOR LIQUID FILLED ANNULAR SPACE TANKS - AIR/SOAP TESTS ON ACCESSORIES AND FITTINGS CAN BE PERFORMED AFTER THE TANK IS IN
<br />THE EXCAVATION BEFORE OR AFTER BACKFILLING.
<br />CONTRACTOR SHALL COMPLETE ALL TESTING ACCORDING TO MANUFACTURER'S INSTRUCTIONS FOR THE TANKS. CONTRACTOR SHALL COMPLETE ALL
<br />WARRANTY VALIDATION TESTING AND PROVIDE DOCUMENTATION TO OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER.
<br />HYDROSTATICALLY MONITORED DOUBLE WALL TANKS SHALL BE TESTED ACCORDING TO MANUFACTURER'S INSTRUCTIONS BY:
<br />- INSPECT AND ADJUST RESERVOIR LEVEL OF THE MONITORING FLUID (TO COVER THE RIBE INSIDE THE RESERVOIR.
<br />- REMOVE ENOUGH TANK FITTING PLUGS TO SEE INSIDE THE PRIMARY TANK. VISUALLY INSPECT THE TANK INTERIOR FOR COLORED MONITORING
<br />FLUID TRACES.
<br />- CONNECT TANK TEST MANIFOLD AND PRESSURIZE THE PRIMARY TANK TO 5 PSIG MAX. (3 PSIG MAX. FOR 12' TANKS). MONITOR THE
<br />PRESSURE FOR 30 MINUTES FOR ANY LOSS IN PRESSURE THAT MAY INDICATE A LEAK.
<br />- DO NOT PRESSURIZE THE ANNULAR SPACE. DOING SO MAY DAMAGE THE PRIMARY TANK OR CAUSE TANK FAILURE.
<br />- WHILE UNDER PRESSURE, COVER FITTINGS AND MANWAY(S) WITH SOAP SOLUTION AND INSPECT.
<br />- AFTER COMPLETING AIR TEST, RELEASE PRESSURE; REMOVE ALL GAUGES, VALVES, AND HOSE ASSEMBLIES; REPLACE AND TIGHTEN FITTING
<br />PLUGS; AND REPLACE THE PLASTIC VENT PLUG IN THE OPEN FITTINGS.
<br />***NOTE*** HYDROSTATIC FLUID RESERVOIR LEVEL MUST BE RECHECKED TO VERIFY TANK INTEGRITY PRIOR TO INTRODUCING BALLAST INTO TANKS.
<br />FIELD REPAIR OF TANKS: IT IS ALLOWABLE TO FIELD REPAIR DAMAGED TANKS AFTER APPROVAL BY BP FILED ENGINEER. ALL TANKS DAMAGED IN
<br />TRANSPORT OR OFF LOADING OPERATIONS SHALL BE FIELD REPAIRED BY A TANK MANUFACTURER'S CERTIFIED FIELD SERVICE REPRESENTATIVE. TANK
<br />MANUFACTURER SHALL RE -CERTIFY REPAIRED TANKS FOR USE. ALL FIELD SERVICE WORK SHALL BE DOCUMENTED. COPIES OF ANY AND ALL FIELD
<br />SERVICE DOCUMENTATION SHALL BE PLACED IN THE PROJECT FILE AND INTO OWNERS OPERATING FILE.
<br />TANK MEASUREMENTS:
<br />THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE COMPLETION OF THE FOLLOWING TANK MEASUREMENT ACTIVITIES:
<br />1. VERIFY THE EXTERNAL SIZE OF THE TANK TO MATCH WITH MANUFACTURER SUPPLIED SHOP MEASUREMENTS.
<br />TRANSFER THE SIZE, SERIAL NUMBER, AND PRODUCT INSTALLED, AND POSITION OF TANK TO THE AS -BUILT PLAN.
<br />2. TRANSFER TANK DIMENSIONAL AND PRODUCT INFORMATION TO THE DATA SHEET IN THE TANK GAUGE CONSOLE.
<br />3. PROVIDE THE TOP OF TANK ELEVATION READING AT BOTH ENDS OF EACH TANK.
<br />TANK DEFLECTION MEASUREMENT PROCEDURE:
<br />DEFLECTION MEASUREMENT BEFORE AND AFTER TANK INSTALLATION SHALL BE ACCORDING TO MANUFACTURER'S REQUIREMENTS AND SHALL BE
<br />WITHIN MANUFACTURER'S TOLERANCES. ALL INFORMATION SHALL BE COMPLETED AS PER THE MANUFACTURER'S WARRANTY DOCUMENTATION.
<br />I.D.="A"
<br />BEFORE BACK FILL AFTER BACK FILL
<br />TANK INSPECTION AND INSTALLATION - DEFLECTION MEASUREMENT
<br />DIPSTICK PREPARATION
<br />DRIVE A SMALL HEADED, NON -SPARKING (E.G. BRASS) NAIL HALFWAY INTO A WOODEN DIPSTICK, 1 INCH ABOVE ITS BASE.
<br />FIRST DIAMETER READING (PRIOR TO BACK FILL)
<br />1. PLACE THE DIPSTICK INTO A SERVICE FITTING.
<br />2. MEASURE AND RECORD THE DISTANCE FROM THE TANK BOTTOM TO THE TOP OF THE FITTING.
<br />3. PULL THE DIPSTICK UP UNTIL THE EXPOSED NAIL CATCHES ON THE INSIDE TOP OF TANK.
<br />4. MEASURE THE DISTANCE FROM THE TANK TOP (INSIDE) TO THE TOP OF THE FITTING. SUBTRACT 1 INCH FROM THIS MEASUREMENT AND
<br />RECORD THE DISTANCE.
<br />5. SUBTRACT THE SECOND DISTANCE FROM THE FIRST AND RECORD THIS VALUE AS READING "A" ON THE INSTALLATION CHECKLIST.
<br />SECOND DIAMETER READING (AFTER BACKFILL)
<br />1. PLACE THE DIPSTICK INTO A SERVICE FITTING WITH A STANDPIPE INSTALLED TO SUBGRADE.
<br />2. MEASURE AND RECORD THE DISTANCE FROM THE TANK BOTTOM TO THE TOP OF THE STANDPIPE.
<br />3. PULL THE DIPSTICK UP UNTIL THE EXPOSED NAIL CATCHES ON THE INSIDE TOP OF TANK.
<br />4. MEASURE THE DISTANCE FROM THE TANK TOP (INSIDE) TO THE TOP OF THE STANDPIPE. SUBTRACT 1 INCH FROM THIS MEASUREMENT AND
<br />RECORD THE DISTANCE.
<br />5. SUBTRACT THE SECOND DISTANCE FROM THE FIRST AND RECORD THIS VALUE AS READING "B" ON THE INSTALLATION CHECKLIST.
<br />CALCULATION AND COMPARISON
<br />1. SUBTRACT READING "B" FROM READING "A".
<br />2. COMPARE THIS VALVE TO THE TABLE OF "MAXIMUM ALLOWABLE DEFLECTIONS" SHOWN ON THE "INSTALLATION CHECKLIST".
<br />3. VERTICAL DEFLECTION IN EXCESS OF THESE VALUES INDICATES IMPROPER INSTALLATION AND VOIDS THE TANK WARRANTY.
<br />MAXIMUM DEFLECTION FOR 8'-0" TANKS = 1-1/4"
<br />MAXIMUM DEFLECTION FOR 10'-0" TANKS = 1-1/2"
<br />TOP OF TANK ELEVATION:
<br />CONTRACTOR TO CALCULATE TOP OF TANK ELEVATION. START WITH 18" MINIMUM DEPTH OF VAPOR RECOVERY LINE AT THE FARTHEST DISPENSER
<br />AND SLOPE 1/4" PER FOOT MAXIMUM TO 1/8" PER FOOT MINIMUM. ADD 12" AT THE TANK. ADD 13" (FOR 3" PIPE) OR 8" (FOR 2") FOR A
<br />CHANGE IN PIPING DIRECTION OTHER THAN 90 OR 45 DEGREES. SET TANKS 6" DEEPER THAN CALCULATED AS PRECAUTION. IN NO EVENT SHALL
<br />THE TANK BE BURIED LESS THAN 4'-0" BELOW FINISHED GRADE OR DEEPER THAN 7'-0" BELOW FINISHED GRADE. SEE MANUFACTURERS
<br />INSTALLATION INSTRUCTIONS FOR MINIMAL TANK BURY WHEN DEADMEN ANCHORING IS NOT PROVIDED. ANY VARIATIONS IN SLOPE FROM 1/4" PER
<br />FOOT SHALL BE REPORTED TO OWNER'S ENGINEER.
<br />TANK EXCAVATION:
<br />CONTRACTOR TO EXCAVATE TANK HOLE. CONTRACTOR SHALL ADHERE TO O.S.H.A. STANDARDS ON EXCAVATIONS. CONTRACTOR MAY SELECT ANY OF
<br />THE RECOMMENDED PRACTICES FOR TANK EXCAVATION AND MUST PROVIDE ALL NECESSARY PROTECTIVE BARRICADES.
<br />SLOPE SIDES OF TANK HOLE (USE OF SLOPING MUST BE RECEIVE PRIOR APPROVAL ON INDIVIDUAL SITE BASIC FROM "BP") OR USE
<br />SHORING FOR ALL TANK EXCAVATIONS IN ACCORDANCE WITH OSHA 1926 SUBPART P, OSHA STANDARDS - EXCAVATIONS; FINAL RULE
<br />OCTOBER 1, 1989. WHEN ENGINEERED SHORING IS REQUIRED DUE TO SITE CONDITIONS AN ENGINEERED SHORING PLAN UTILIZING
<br />INTERLOCKING STEEL SHEET PILING SHALL BE PROVIDED AND SHALL INCLUDE SUPPORTING ENGINEERING CALCULATIONS BY A STATE
<br />CERTIFIED ENGINEER AND SHALL BE THE RESPONSIBILITY OF THE INSTALLING CONTRACTOR.
<br />GENERAL CONTRACTOR SHALL OBTAIN NECESSARY PERMIT FROM APPLICABLE AGENCIES FOR EXCAVATIONS OF TRENCHES 5'-0" OR MORE
<br />IN DEPTH INTO WHICH A PERSON IS REQUIRED TO DESCEND.
<br />TANK EXCAVATIONS SHALL BE THE MINIMUM SIZE REQUIRED TO PROVIDE FOR BEDDING AND CLEARANCES INDICATED IN THESE DRAWINGS. TANK
<br />BURIAL DEPTH FIELD DETERMINED TO PROVIDE FOR 1/4" (1/8" PER FOOT MIN.) PER FOOT FOR STAGE II VAPOR RECOVERY PIPING & 1/8"
<br />MINIMUM PER FOOT FOR PRODUCT PIPING SLOPE BACK FROM DISPENSERS TO TANK.
<br />TANK STABILITY BUOYANCY CALCULATIONS:
<br />TANK STABILITY SHALL BE RE -CHECKED AGAINST FLOATATION BY INSTALLING CONTRACTOR. SEE BUOYANCY CALCULATIONS ON TANK DETAILING SHEETS.
<br />TANK ANCHORING:
<br />CONTRACTOR TO INSTALL MANUFACTURER SUPPLIED TANK HOLD DOWN STRAPS & ANCHORS WHEN REQUIRED DUE TO HIGH WATER TABLE, LOCAL
<br />REGULATIONS, OR SPECIFIED BY SITE ENGINEER/DESIGNER AND/OR OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER. WHEN
<br />REQUIRED, THE ANCHORING SYSTEM SHALL BE IN COMPLIANCE WITH AUTHORITY HAVING JURISDICTION. ANCHOR & STRAPS TO BE INSTALLED ACCORDING TO
<br />MANUFACTURER'S INSTRUCTIONS.
<br />** ALTERNATE ANCHORING BY USE OF A CONCRETE ANCHORING SLAB IS PERMITTED. WHEN GROUNDWATER LEVEL IS ANTICIPATED TO BE
<br />WITHIN 5 FT. OF GRADE CONTRACTOR SHALL NOTIFY OWNER'S REPRESENTATIVE FOR DIRECTION ON ANCHORING METHOD TO BE USED
<br />(DEADMAN OR ANCHORING SLAB) AND SUCH SHALL BE INSTALLED ACCORDING TO MANUFACTURER'S RECOMMENDATION.
<br />** THIS PROCEDURE IS REQUIRED IN NYC AND CONSIDERED PART OF SCOPE OF WORK WHEN INSTALLING TANKS IN NYC.
<br />NYC VARIANT: IT IS THE CONTRACTORS RESPONSIBILITY TO PROVIDE FOR THE INSTALLATION OF A 12" CONCRETE ANCHORING SLAB. 4,000
<br />PSI AT 28 DAYS WITH (2) LAYERS OF 6x6-w5.5xw5.5 ON 2" STEEL CHAIRS TOP & BOTTOM
<br />FILTER FABRIC: IT IS THE CONTRACTORS RESPONSIBILITY TO PROVIDE FOR THE INSTALLATION OF FILTER FABRIC (DUPONT TYPAR OR MIRAFI
<br />50OX ) WHICH IS REQUIRE FOR WET HOLE INSTALLATIONS OR UNSUITABLE SOILS. (NOTE: A WET HOLE/ UNSUITABLE AREA REQUIRING
<br />FILTER FABRIC IS ANY TANK EXCAVATION IN WHICH THE AREA IS SUBJECT TO: TIDAL INFLUENCES, OR AREAS SUBJECT TO FREQUENTLY
<br />CHANGING GROUND WATER LEVELS, OR WATER CONDITIONS WITH SILTY SOIL, OR MUCK, BOG, PEAT, SWAMP, LANDFILL TYPE AREAS OR
<br />ANY OTHER SITUATION WHERE THE SOIL IS INHERENTLY UNSTABLE, OR SOILS WITH LESS THAN 250 LBS./SQ. FT. COHESION, OR WITH
<br />ULTIMATE BEARING CAPACITY OF LESS THAN 500 LBS./SQ. FT., OR AT THE REQUEST OF THE TANK OWNER. ALL WET HOLE BALLAST
<br />INSTALLS (AS DESCRIBED IN SECTION BELOW) SHALL USE FILTER FABRIC.
<br />FILTER FABRIC SHALL EXTEND 1 FOOT ABOVE MAX HIGH WATER TABLE AND SEAMS SHALL BE OVERLAPPED BY 1 FOOT. MATERIAL SHALL
<br />BE PINNED OR OTHERWISE SECURED ALLOW BACKFILL WITHOUT DISTURBANCE. USE OF PLASTIC, OR ANY OTHER MATERIAL THAT MAY TEAR,
<br />OR DEGRADE OVERTIME IS PROHIBITED.
<br />WET HOLE BALLAST METHOD:
<br />WATER IS THE SUITABLE MEDIUM FOR BALLAST DURING WET HOLE TANK INSTALLATIONS. A PROPERLY INSTALLED 12 FOOT HIGH TEMPORARY VENT PIPE
<br />MUST BE INSTALLED BY THE CONTRACTOR. IF WATER IS USED TO BALLAST TANKS, THE WATER IS TO BE COMPLETELY PUMPED OUT & MOPPED DRY IN
<br />ORDER TO PROTECT FUEL INTEGRITY. CONTRACTOR IS REQUIRED TO COORDINATE BALLASTING OPERATIONS WITH OWNER'S REPRESENTATIVE OR HIS AGENT,
<br />>
<br />THE BP PROJECT MANAGER. IT IS THE INSTALLING CONTRACTOR'S RESPONSIBILITY TO DETERMINE THE JURISDICTIONAL REQUIREMENTS AND ACCEPTANCE
<br />FOR BALLASTING THE TANKS AND TO PROVIDE FOR PROPER DISPOSAL OF THE BALLASTING MEDIUM UNDER THE REGULATIONS OF THE GOVERNING
<br />AUTHORITY.
<br />BACK FILL:
<br />CONTRACTOR TO PROVIDE ALL BACK FILL REQUIRED FOR THE PROJECT SCOPE. PEA GRAVEL SHALL CONSIST OF NATURALLY ROUNDED AGGREGATE,
<br />MINIMUM 1/8" AND MAXIMUM 3/4" SIZE. FREE OF CLAY, SLAG, CINDERS, OR DEBRIS. ALL SUBSTITUTES MUST BE APPROVED BY MANUFACTURER AND
<br />OWNERS FIELD REPRESENTATIVE.
<br />NO MORE THAN 5% (BY WEIGHT) MAY PASS THE #8 SIEVE FOR BACK FILLING NONMETALLIC TANKS WITH A 96% TO 98% FREE FALL COMPACTION. DRY
<br />PEA GRAVEL DENSITY MINIMUM OF 95 POUNDS PER CUBIC FOOT IS REQUIRED. SUPPLY QUARRY CERTIFICATION MEETING ASTM C-33, PARAGRAPH 9.1
<br />REQUIREMENTS.
<br />BACK FILLING OF TANK EXCAVATIONS SHALL BE PROVIDED IN LIFTS AS PER TANK MANUFACTURER'S INSTALLATION INSTRUCTIONS.
<br />PRODUCT, VENT, AND VAPOR PIPING SHALL BE LAID AND CONTINUOUSLY SUPPORTED ON A 6" BED OF COMPACTED PEA GRAVEL. BLOCKS, PLANKS,
<br />OR OTHER DEBRIS SHALL NOT BE USED TO SUPPORT PIPING IN FINAL INSTALLATION.
<br />NOTE: UNDER NO CIRCUMSTANCES SHALL DIRT, PAVING MATERIALS, WOOD, OR OTHER CONSTRUCTION DEBRIS BE ALLOWED TO REMAIN IN TANK AND
<br />PIPE EXCAVATIONS.
<br />(2) ANNULAR SPACE HYDROSTATIC MONITOR AND RISER INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL 4" FIBERGLASS RISER AND VEEDER ROOT HYDROSTATIC SENSOR AT TANK ANNULAR SPACE LOCATION NOTED
<br />ON THE PLANS PER MANUFACTURERS INSTRUCTIONS.
<br />(3) TANK SUMP INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL 42" OR 48" DIAMETER TURBINE SIDE FIBERGLASS POLYSIDED SUMPS ON TANKS PER MANUFACTURER'S
<br />INSTRUCTIONS. NOTE THAT THE ORIENTATION OF THE TANK SUMPS MUST BE CORRECT IN ORDER TO FACILITATE CORRECT PIPING INSTALLATION INTO
<br />THE SUMPS. SEE ACCOMPANYING DETAILS IN PLAN SET AND NOTE SIZES OF SUMPS PER PROJECT DEMOGRAPHICS.
<br />NYC VARIANT: 42" DIAMETER TURBINE SUMPS ARE INSTALLED.
<br />LONG ISLAND/NY VARIANT: ON TANKS INSTALLED IN LONG ISLAND, FILL SUMPS ARE REQUIRED. SEE ENCLOSED DRAWINGS FOR DETAILS
<br />ARCO BRANDED VARIANT: 48" DIAMETER TURBINE SUMPS ARE INSTALLED.
<br />CALIFORNIA VARIANT: 42" DIAMETER FILL SUMPS TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS HYDROSTATIC MONITORING DEVICE PER
<br />AB -2481 REQUIREMENTS.
<br />(4) TANK LEVEL GAUGE / OVERFLOW PROTECTION:
<br />STANDARD: CONTRACTOR TO INSTALL VEEDER ROOT MAGNOSTRICTIVE PROBE LEVEL GAUGE AT LOCATION NOTED ON PLANS PER MANUFACTURER'S
<br />INSTALLATION INSTRUCTIONS.
<br />OVERFLOW PROTECTION: UST OVERFLOW COMPLIANCE IS ACHIEVED BY USE OF OVERFLOW PREVENTION DROP TUBE FLAPPER VALVE SET AT 95% AND
<br />IS IN ACCORDANCE WITH FEDERAL AND STATE GUIDELINES FOR UST OVERFILL REQUIREMENTS.
<br />AN OVERFILL ALARM AND ACKNOWLEDGE SWITCH TIED INTO THE VEEDER ROOT AUTOMATIC TANK GAUGE SYSTEM. THE MONITORING SYSTEM PROVIDES
<br />AN AUDIBLE AND VISUAL ALARM WHEN THE TANK(S) ARE FILLED TO THE 90% LEVEL.
<br />(5) FILL AND STAGE I VAPOR RECOVERY INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL 4" GALVANIZED FILL AND STAGE I VAPOR RECOVERY RISERS. CONTRACTOR TO INSTALL DROP TUBE ASSEMBLY.
<br />WITH OVERFILL PREVENTION DROP TUBE. CONTRACTOR TO INSTALL VENT AND STAGE II FLEX CONNECTORS AND FRP ADAPTERS. LOCATE AND CUT
<br />PENETRATIONS INTO SUMPS FOR THE ROUTING OF VENT AND STAGE II VAPOR PIPING INTO TURBINE SUMPS AND MAKE CONNECTIONS TO VENT AND
<br />VAPOR PIPING FIBERGLASS PIPING. CONTRACTOR TO INSTALL DOUBLE SIDED PENETRATION ENTRY BOOTS FOR ALL ENTRIES INTO SUMPS. CONTRACTOR
<br />TO INSTALL STATIC GROUNDING SYSTEM AT ALL FILL AND VAPOR RISERS PER INSTALLATION DETAILS SHOWN ON SHEET G.0.7.
<br />CONTRACTOR TO INSTALL CARB APPROVED STAGE I MANHOLES WITH 5 GALLON SPILL COLLECTION BUCKETS. INSTALL PRODUCT AND FILL ADAPTERS AND
<br />CAPS. SEE ACCOMPANYING DETAILS IN SITE SPECIFIC PLAN SET FOR MANUFACTURER AND INSTALLATION REQUIREMENTS.
<br />NYC VARIANT: CONTRACTOR TO PROVIDE THE INSTALLATIONS OF A SEPARATE UNOBSTRUCTED VENT CONNECTION AT EACH TANK AT THE TURBINE SIDE
<br />OF THE TANK AS PER PLANS AND PER NYC CODE REQUIREMENTS. A 15 GALLON PRODUCT SPILL COLLECTION BUCKET IS REQUIRED BY NYC FIRE
<br />CODE. FILL SPILL BUCKETS MUST HAVE A NYC CERTIFICATE OF APPROVAL FROM FIRE DEPARTMENT.
<br />6) TURBINE INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL FE PETRO IST 2 HP VARIABLE SPEED TURBINES AND PIPING CONNECTION VALVES AND FITTINGS IN TANK
<br />SUMPS AS SHOWN ON SITE SPECIFIC DETAIL DRAWINGS. ALL PRODUCT LINES TO TURBINES TO BE EQUIPPED WITH 3 GPH ELECTRONIC LINE LEAK
<br />DETECTION. LEAK DETECTORS ARE TO BE TESTED FOR THE 3 GPH LEAK DETECTION PRIOR TO START UP. CONTRACTOR TO PROVIDE TEST DATA AT
<br />THE TIME OF PUNCH LIST AS WELL AS INCLUDE IN CLOSE OUT BINDER. ALL TURBINES ARE EQUIPPED WITH STANDARD "R" CHECK VALVE AS A
<br />STANDARD FROM FACTORY. SET TURBINE INTAKES AT 5" FROM BOTTOM OF TANKS. TURBINES TO BE EQUIPPED WITH INTAKE FILTER SCREENS.
<br />CONTRACTOR TO INSTALL 1" RIGID STEEL CONDUITS FOR SUBMERSIBLE PUMP POWER. (ONE FOR EACH TURBINE). CONTRACTOR IS TO LABEL
<br />TURBINES AND CONTROLLERS AS TO WHICH PRODUCT THEY SERVE. GREEN CONTROLLER LIGHTS ARE TO GO OUT WHEN TURBINES ARE OFF OR
<br />LOSE POWER. IST PUMP CONTROLS ARE TIED TO VEEDER ROOT CONTROL PANEL. SEE APPROPRIATE TURBINE CONFIGURATION AND PROGRAMMING
<br />SHEETS.
<br />SINGLE MASTER TURBINE CONFIGURATIONS - EQUIPPED AS NOTED ABOVE. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />MASTER -SATELLITE TURBINE CONFIGURATIONS - EQUIPPED AS NOTED ABOVE EXCEPT: ONLY THE MASTER TURBINE SHALL HAVE THE PLLD LEAK
<br />DETECTOR INSTALLED. CONTRACTOR TO REMOVE THE STANDARD "R" CHECK VALVE OUT OF THE SATELLITE TURBINE. THE BALL VALVE ON MANIFOLD
<br />LINE BETWEEN TURBINES SHALL BE SET IN THE "OPEN" POSITION AND A SINGLE PLLD (PART #848-480-001) IS TO BE INSTALLED ON THE
<br />MASTER IST WITH AN FE. PETRO NON -VENTED PRECISION CHECK VALVE (PART #65 PSI) INSTALLED ON THE SATELLITE IST PREVENTING
<br />BACKFILLING OF USTs. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />MASTER -MASTER TURBINE CONFIGURATIONS - EQUIPPED AS NOTED ABOVE EXCEPT: THE BALL VALVE ON MANIFOLD LINE BETWEEN TURBINES SHALL
<br />BE SET IN THE "CLOSED" POSITION DURING NORMAL OPERATION. SEPARATE LINES & (2) PLLDs (PART #VER -848-480-001) SHALL BE INSTALLED.
<br />IN CASE OF FAILURE OF AN INDIVIDUAL IST, THE PRODUCT CROSS-OVER LINE CAN BE PLACED INTO OPERATION BY OPENING THE CROSS
<br />CONNECTING VALVE. THE FAILED IST MUST HAVE ITS PLLD DISABLED & DISPENSER SIGNAL WIRES NEED TO BE MODIFIED FOR THIS TEMPORARY
<br />SET-UP. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />ARCO LARGE SITE VARIANT - IF SITE HAS 9 OR MORE MPDS, TWO (2) 2 HP VARIABLE SPEED TURBINES ARE TO BE INSTALLED IN THE PRIMARY
<br />REGULAR UNLEADED TANK. THE REGULAR UNLEADED TURBINES SHALL BE SET UP AS "MASTER/SATELLITE/SATELLITE" AND THE CROSS CONNECTION
<br />MANIFOLD BETWEEN TANKS SHALL BE OPENED ALLOWING ALL THREE TURBINES TO SERVE THE ENTIRE SITE.
<br />NYC VARIANT: MASTER -MASTER TURBINE CONFIGURATION W/ ROTATING STARTS - EQUIPPED AS NOTED ABOVE FOR MASTER -SATELLITE
<br />CONFIGURATION EXCEPT WITHOUT SIPHON LINE BETWEEN TANKS: THE UST PRODUCT LEVEL BALANCING IS ACHIEVED BY ROTATING THE STARTING OF
<br />INDIVIDUAL IST'S WITH CONTROL LOGIC LINKED TO THE VEEDER ROOT ATG. THE PRODUCT LINES ARE CONNECTED BY A CROSS OVER MANIFOLD
<br />BETWEEN TURBINES. ONE IST, THE MASTER, SHALL HAVE A PLLD LEAK DETECTION DEVICE INSTALLED (PART #VER -848-480-001) AND THE
<br />SATELLITE SHALL HAVE AN FE PETRO NON -VENTED PRECISION CHECK VALVE (PART #65 PSI) INSTALLED. THE BALL VALVE ON MANIFOLD LINE
<br />BETWEEN TURBINES SHALL BE SET IN THE "OPEN" POSITION DURING NORMAL OPERATION. IN CASE OF FAILURE OF AN INDIVIDUAL IST, NO
<br />ADJUSTMENT TO THE DISPENSER SIGNAL WIRES WILL BE REQUIRED AS THE IST CONTROLLERS WILL ACCOMMODATE THE IST STARTING VIA THE
<br />VEEDER ROOT ATG LINK. THE PRODUCT IN THE UST WITH THE FAILED IST WILL HAVE THE PRODUCT LEFT IN A STATIC STATE AND NOT AVAILABLE
<br />FOR DISPENSING UNTIL A REPAIR IS MADE. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />(7) SIPHON LINE INSTALLATION:
<br />STANDARD: WHEN SITE SPECIFIC TANK CONFIGURATION SHOWS MULTIPLE TANKS FOR IDENTICAL PRODUCTS, CONTRACTOR TO INSTALL 4" OVER 3"
<br />DOUBLE WALL FIBERGLASS SIPHON LINES AND PIPING CONNECTION VALVES AND FITTINGS BETWEEN TANKS. INSTALL SIPHON PIPING AS LOW AS
<br />POSSIBLE IN SUMP. NOTE LIMITATION ON MAXIMUM SIPHON PIPING SYSTEM HEIGHT ON DETAILS. ADJUST HEIGHT DOWN FOR SMALLER DIAMETER
<br />TANKS. CONTRACTOR TO INSTALL VEEDER ROOT SIPHON BREAK, IF APPROPRIATE FOR MARKET CONDITIONS. SEE APPROPRIATE SITE SPECIFIC
<br />DRAWINGS FOR INSTALLATION DETAILS.
<br />NYC VARIANT: SIPHON PIPING IS NOT INSTALLED. SEE TURBINE INSTALLATION NOTE ABOVE. SEE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />ARCO BRANDED VARIANT: CONTRACTOR TO INSTALL 4" OVER 3" DOUBLE WALL FIBERGLASS SIPHON PIPING. SIPHON BREAK IS NOT INSTALLED.
<br />INSTALL SIPHON PIPING AS LOW AS POSSIBLE IN SUMP. NOTE LIMITATION ON MAXIMUM SIPHON PIPING SYSTEM HEIGHT ON DETAILS. ADJUST
<br />HEIGHT DOWN FOR SMALLER DIAMETER TANKS. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS.
<br />CALIFORNIA VARIANT: SIPHON PIPING TO BE INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB -2481 REQUIREMENTS
<br />(8) PRODUCT PIPING INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL DOUBLE WALL FIBERGLASS PRODUCT PIPING, CONNECTORS, VALVES AND FITTINGS IN TANK AND DISPENSER
<br />SUMPS AS SHOWN ON SITE SPECIFIC DETAIL DRAWINGS TO SUPPLY DISPENSERS. PRODUCT PIPING TO BE N.O.V. RED THREAD IIA, 2" INSIDE 3"
<br />DIAMETER AS INDICATED ON SITE SPECIFIC FUELING PLAN. ALL PIPING AND FITTINGS SHALL BE UL -971 LISTED IN COMPLIANCE WITH THE JULY 2005
<br />PERFORMANCE STANDARDS, AND SHALL BE COMPATIBLE WITH ETHANOL, INCLUDING BUT NOT LIMITED TO "FLEX FUEL" (85% ETHANOL 15% GASOLINE).
<br />PRODUCTS LINES TO BE EQUIPPED 3 GPH PRESSURE LINE LEAK DETECTORS (PLLD) ON TURBINES AND WITH LIQUID LEAK MONITORING SENSORS
<br />LOCATED IN TURBINE PIPING SUMPS ATTACHED TO TANKS WIRED FOR TURBINE SHUT DOWN. PRODUCT PIPING IN TURBINE SUMPS, PRODUCT PIPING
<br />CROSS CONNECTION MANIFOLDS BETWEEN SUMPS AND SIPHON PIPING PENETRATIONS ARE TO ENTER THE SAME SIDE OF THE SUMP IF POSSIBLE. IF
<br />PRODUCT PENETRATION ENTERS ON BOTH SIDES OF SUMP DUE TO FIELD CONDITIONS, THEN DUAL SENSORS AT TURBINE SUMP MAY BE REQUIRED
<br />TO BE INSTALLED BY LOCAL REGULATIONS. IF THE BP PROJECT MANAGER DETERMINES THAT THE ALL THE PIPING ENTRIES NOTED ABOVE COULD
<br />HAVE BEEN MADE TO THE SAME SIDE OF THE SUMP, THEN ANY COSTS ASSOCIATED WITH EXTRA SENSORS SHALL BE BORNE BY THE INSTALLING
<br />CONTRACTOR. PIPING TO BE INSTALLED WITH A SLOPE OF 1/8" PER FOOT MINIMUM TO TANKS UNLESS APPROVED BY OWNER. CONTRACTOR TO
<br />INSTALL TRACER TAPE WITH PRODUCT PIPING PER TRENCHING DETAILS. PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH DOUBLE WALL FRP
<br />ENTRY FITTINGS. TESTING OF PRODUCT LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE STATION OPERATION. SEE
<br />SITE SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS.
<br />***NOTE*** "FIBERCAST SYSTEMS" PIPING TO BE INSTALLED PER MANUFACTURER'S INSTALLATION MANUAL AND SHALL ONLY BE INSTALLED BY
<br />QUALIFIED INSTALLERS CERTIFIED BY THE MANUFACTURER.
<br />CALIFORNIA VARIANT: IN ADDITION TO THE ABOVE, PIPING TO BE INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB -2481
<br />REQUIREMENTS
<br />(9) VENT PIPING INSTALLATION:
<br />STANDARD: CONTRACTOR TO INSTALL 2" INDIVIDUAL SINGLE WALL FIBERGLASS VENT PIPING, CONNECTORS, VALVES AND FITTINGS ON TANKS AS
<br />INDICATED ON SITE SPECIFIC FUELING PLAN AND ACCOMPANYING DETAILS. CONTRACTOR TO PROVIDE AT LEAST 4 FEET OF PIPING RUN BEFORE A
<br />CHANGE OF DIRECTION OF 30 DEGREES OR MORE IN ORDER TO PROVIDE MECHANICAL FLEXIBILITY PER CODE REQUIREMENTS. CONTRACTOR TO
<br />INSTALL TRACER TAPE WITH VENT PIPING PER TRENCHING DETAILS. PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH SINGLE WALL ENTRY
<br />FITTINGS. VENT PIPING SHALL BE DESIGNED AND INSTALLED FOR SLOPE 1/4" PER FOOT MINIMUM BACK TO TANKS. FOR LONG PIPING RUNS 1/8"
<br />PER FOOT IS ACCEPTABLE.
<br />CONTRACTOR TO INSTALL ABOVE GROUND RISERS AND MOUNTING RACK AS DETAILED ON THESE PLANS. TERMINATION POINT OF TANK VENTS TO BE
<br />A MINIMUM OF 12' ABOVE GRADE AND NOT WITHIN 5' FROM ANY BUILDING OPENING OR PROPERTY LINE THAT CAN BE BUILT UPON. VENT RISERS
<br />SHALL BE INSTALLED IN ACCORDANCE WITH NFPA-30, INTERNATIONAL AND UNIFORM FIRE CODE REQUIREMENTS AND CARB EVR REQUIREMENTS.
<br />CONTRACTOR TESTING OF VENT LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE STATION OPERATION. SEE SITE
<br />SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS. SEE FIBERGLASS PIPING MANUFACTURER SPECIFICATION BELOW.
<br />t•1n 9115
<br />FIBERCAST SYSTEMS: RED
<br />THREAD II PIPE AND FITTINGS
<br />(USED FOR SINGLE WALL). WHERE
<br />DOUBLE WALL SYSTEMS ARE REQUIRED FOR ALL VENT
<br />AND VAPOR PIPING, USE
<br />SIZE OVER SIZE RED THREAD
<br />II PIPING AND FITTINGS. USE
<br />ONLY
<br />FIBERCAST SYSTEMS ALCOHOL COMPATIBLE ADHESIVES.
<br />ALL PIPING AND FITTINGS
<br />SHALL BE UL -971 LISTED IN
<br />COMPLIANCE WITH THE JULY
<br />2005
<br />PERFORMANCE STANDARDS.
<br />PIPING TO BE INSTALLED
<br />PER MANUFACTURER'S LISTED
<br />INSTRUCTIONS AND SHALL ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE
<br />MANUFACTURER. PROVIDE
<br />AT LEAST 4' OF STRAIGHT PIPING
<br />RUN BEFORE A CHANGE
<br />OF DIRECTION
<br />OF MORE THAN 30 DEGREES AND INSTALL
<br />FLEXIBLE CONNECTORS AT THE VENT AND VAPOR CONNECTION AT THE TANK SUMPS,
<br />AND
<br />DISPENSER SUMPS.
<br />NYC VARIANT: SAME AS ABOVE EXCEPT: VENT CONNECTIONS ARE ROUTED TO A SEPARATE UNOBSTRUCTED EXTRACTOR FITTING LOCATED IN THE
<br />TURBINE SIDE. VENT TERMINATION TO BE A MINIMUM OF 15' ABOVE GRADE.
<br />JURISDICTIONAL VARIANT: INSTALL DOUBLE WALL SIZE OVER SIZE FIBERGLASS PIPING WHEN REQUIRED BY AUTHORITY HAVING JURISDICTION.
<br />CALIFORNIA VARIANT: VENT PIPING TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB -2481
<br />REQUIREMENTS
<br />STANDARD: CONTRACTOR TO INSTALL 3" SINGLE WALL FIBERGLASS STAGE II VAPOR RECOVERY HEADER, CONNECTORS, VALVES AND FITTINGS TO THE
<br />LOWEST OCTANE GRADE AS INDICATED ON SITE SPECIFIC FUELING PLAN AND ACCOMPANYING DETAILS. NOTE THAT THE 1ST CONNECTION FROM STAGE
<br />II VAPOR RECOVERY HEADER TO LOWEST OCTANE TANK SHALL BE 3". ALL OTHER CONNECTIONS TO ADDITIONAL TANKS SHALL BE MADE WITH 2".
<br />CONTRACTOR TO INSTALL 3" TO 2" REDUCING TEES WHERE HEADERS BRANCH TO DISPENSERS. MAXIMUM (2) DISPENSERS PER 2" BRANCH.
<br />CONTRACTOR TO PROVIDE AT LEAST 4 FEET OF STRAIGHT PIPING RUN BEFORE A CHANGE OF DIRECTION OF 30 DEGREES OR MORE IN ORDER TO
<br />PROVIDE MECHANICAL FLEXIBILITY PER CODE REQUIREMENTS. CONTRACTOR TO INSTALL TRACER TAPE WITH VAPOR PIPING PER TRENCHING DETAILS.
<br />PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH DOUBLE WALL ENTRY FITTINGS. STAGE II VAPOR RECOVERY PIPING SHALL BE DESIGNED AND
<br />INSTALLED FOR 1/4" PER FOOT MINIMUM SLOPE BACK TO TANKS. AT LARGE SITE LAYOUTS, 1/8" PER FOOT MINIMUM IS ACCEPTABLE IF IT AVOIDS
<br />USING A KNOCK OUT SUMP (VAPOR POT) OR HAVING EXCESSIVE TANK DEPTH. CONSULT OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP
<br />PROJECT MANAGER, WHERE DISCREPANCIES OCCUR.
<br />CONTRACTOR TESTING OF STAGE II VAPOR LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE STATION OPERATION.
<br />SEE SITE SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS. SEE FIBERGLASS PIPING MANUFACTURER SPECIFICATION BELOW.
<br />VITO�la10[e>�yaIto19[on_, 9615
<br />FIBERCAST SYSTEMS: RED
<br />THREAD II PIPE AND FITTINGS
<br />(USED FOR SINGLE WALL). WHERE
<br />DOUBLE WALL SYSTEMS ARE REQUIRED FOR ALL VENT
<br />AND VAPOR PIPING, USE
<br />SIZE OVER SIZE RED THREAD
<br />II PIPING AND FITTINGS. USE
<br />ONLY
<br />FIBERCAST SYSTEMS ALCOHOL COMPATIBLE ADHESIVES.
<br />ALL PIPING AND FITTINGS
<br />SHALL BE UL -971 LISTED IN
<br />COMPLIANCE WITH THE JULY
<br />2005
<br />PERFORMANCE STANDARDS.
<br />PIPING TO BE INSTALLED
<br />PER MANUFACTURER'S LISTED
<br />INSTRUCTIONS AND SHALL ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE
<br />MANUFACTURER. PROVIDE
<br />AT LEAST 4' OF STRAIGHT PIPING
<br />RUN BEFORE A CHANGE
<br />OF DIRECTION
<br />OF MORE THAN 30 DEGREES AND INSTALL
<br />FLEXIBLE CONNECTORS AT THE VENT AND VAPOR CONNECTION AT THE TANK SUMPS,
<br />AND
<br />DISPENSER SUMPS.
<br />JURISDICTIONAL VARIANT: INSTALL DOUBLE WALL SIZE OVER SIZE FIBERGLASS PIPING WHEN REQUIRED BY AUTHORITY HAVING JURISDICTION.
<br />CALIFORNIA VARIANT: STAGE II VAPOR PIPING TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB -2481
<br />REQUIREMENTS. ALL CONNECTIONS TO THE TANKS SHALL BE MADE WITH 3".
<br />THERE ARE (4) FOUR STAGE II EVR WITH ISD DESIGN CHOICES THAT MAY BE INCORPORATED INTO THE UST SYSTEMS IN CALIFORNIA.
<br />1. VEEDER ROOT CARBON CANISTER VAPOR POLISHER WITH VST BALANCE HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS.
<br />2. HEALY CLEAN AIR SEPARATOR WITH HEALY VACUUM ASSIST HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS.
<br />3. VST ECS VAPOR PROCESSOR WITH VST BALANCE HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS.
<br />4. VST BALANCE HANGING HARDWARE WITH FRANKLIN FUELING/HEALY CLEAN AIR SEPARATOR AND VEEDER ROOT ISD COMPONENTS.
<br />SEE GENERAL SHEETS G.0.6 SERIES DRAWINGS FOR DESIGN INTENT DETAILS ON THE ABOVE SYSTEMS.
<br />NYC VARIANT: STAGE II VAPOR RECOVERY IS CURRENTLY NOT REQUIRED IN NYC & NEW JERSEY MARKET
<br />NOTE: CONTACT BP FUEL SYSTEM DESIGN MANAGER FOR CURRENT STATES NO LONGER REQUIRING STAGE II VAPOR RECOVERY
<br />(10A) DECOMMISSIONING STAGE II VAPOR RECOVERY:
<br />STANDARD: FOR PROJECTS INVOLVING THE DECOMMISSIONING OF STAGE II VAPOR RECOVERY SYSTEMS, G.C. IS TO VERIFY WITH THE AUTHORITY
<br />HAVING JURISDICTION THAT STAGE II IS NO LONGER REQUIRED AT A SPECIFIC FACILITY BEFORE INITIATING THE DECOMMISSIONING WORK AND WHICH
<br />DECOMMISSIONING PROCEDURES ARE REQUIRED TO BE IMPLEMENTED. SEE SHEET G.0.6.15. FOR GENERAL REQUIREMENTS AND PROCEDURES.
<br />CONSULT OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER, WHERE DISCREPANCIES OCCUR BETWEEN THE CONTRACT
<br />DOCUMENTS AND THE REQUIREMENTS OF THE AUTHORITY HAVING JURISDICTION.
<br />CLIENT:
<br />4: bp
<br />'Ad &
<br />lir
<br />ARCO
<br />BP WEST COAST PRODUCTS, LLC
<br />NO.
<br />DATE
<br />DESCRIPTION
<br />0
<br />0
<br />0
<br />0
<br />0
<br />0
<br />0
<br />io
<br />0
<br />0
<br />SEAL:
<br />FESS /0
<br />GH9p�l
<br />N0. 36475
<br />* XP. 6-30-22
<br />ATF
<br />OFF CAUF���
<br />z
<br />Lu
<br />w
<br />•Q
<br />co
<br />U
<br />zoo 0
<br />Z
<br />2E Lu
<br />z co r
<br />0v7rnco
<br />mZ
<br />UOQ
<br />�QU
<br />�
<br />� M Q
<br />fr
<br />QW
<br />I I w�w
<br />}
<br />WZooLL
<br />Ozc
<br />Z
<br />Uz
<br />cozVo
<br />co
<br />7Uo
<br />z
<br />Q
<br />z Q z N
<br />-
<br />WzO-
<br />�w
<br />wQ}�
<br />z Lo Q --
<br />06
<br />z . t
<br />�
<br />Q
<br />w 00 w
<br />O
<br />O
<br />z =
<br />z 0-
<br />z
<br />g
<br />oL
<br />DEVELOPMENT INFORMATION:
<br />SITE ADDRESS:
<br />ADDRESS
<br />2510 S. STATE HWY 99 W. FRONTAGE ROAD
<br />SAN JOAQUIN COUNTY, CA 95205
<br />DESIGNED BY:
<br />CHECKED BY:
<br />DRAWN BY:
<br />ER
<br />DATE:
<br />PROJECT NO:
<br />10/23/2019
<br />DRAWING TITLE:
<br />TANK AND PIPING
<br />SCOPE OF WORK
<br />AND GENERAL NOTES
<br />(FRP 1 OF 3)
<br />SHEET NO:
<br />
|