Laserfiche WebLink
2016 WINTERIZATION PLAN <br /> FOOTHILL LANDFILL <br /> WINTERIZATION TASKS <br /> Following tasks will be completed as part of 2016 winterization: <br /> Area 2A <br /> 1. Winter Pad <br /> A winter pad will be built in Area 2A for refuse disposal during wet weather <br /> (Figure 1). The winter pad will be constructed with six-inches of on-site gravel <br /> base placed on compacted refuse. This task is expected to be completed by end <br /> of October. <br /> 2. Customer Haul Road <br /> The existing customer haul road from the scale house to southern end of Area 1 <br /> is an all-weather road. The extension of the customer haul road from Area 1 to <br /> Area 2A's winter pad has been built with firmly compacted on-site gravel (Figure <br /> 1). <br /> 3. Daily Cover Soil <br /> Daily cover soil is being stockpiled nearby the winter pad for winter operations. <br /> This task is expected to be completed by end of October weather permitting. <br /> 4. Soil Drainage Berms <br /> Soil drainage berms will be installed at the southern edge of Area 2A's top deck <br /> to convey stormwater runoff to the down drains (Figure 1). This task is expected <br /> to be completed by end of November weather permitting. <br /> 5. Grading <br /> The existing top deck of Area 2A will be graded with 3% slope towards the south <br /> to aid stormwater runoff and minimize ponding. This task is expected to be <br /> completed by end of November. <br /> FH-2016-17 winterization Plan Page 1 of 1 Revised 10/4/2016 <br />