6. Our permit coordinator was informed of submittal requirements for this change. <br /> 7. Amended permit application was submitted 10/13/25. <br /> 8. Approved permit was received 10/23/25. <br /> At this point, we are waiting on receipt of the Pneumercator. I have attached ongoing <br /> correspondence with our vendor in getting this order processed. We have been actively working on <br /> this since 10/9/25. As of this morning, we are waiting on Pneumercator to provide us with a current <br /> ETA for the monitor. It is my hope we will receive the monitoring panel within the next couple of <br /> weeks. I will continue to follow up on them in hopes of moving this along and getting a firm ship date. <br /> As soon as we are in receipt of the monitor, we will get this scheduled and I will submit notification for <br /> the final inspection. <br /> Please feel free to let me know if you have any questions or if there is any other information you may <br /> need. <br /> Thank you and have a great weekend. <br /> Tanya Kater <br /> Service Coordinator <br /> SUNWES01- <br /> Direct: 909.970.1150 Cell 909.925.8522 Main: 888.588.8737 ext 8021 Fax: 909.594.6169 <br /> 4780 Cheyenne Way, Chino, CA 91710 <br /> www.sunwestengineering.com <br /> 0 Square [tPd visa w <br /> 2 <br />