TABLE 1: PHASE II ESA ACTIVITY SUMMARY <br /> 125 North Stockton Street, <br /> Lodi,CA <br /> General Tasks Estimated # Activity Stantec Lead Anticipated Comments <br /> Time Frame Subcontractors <br /> 1 Evaluate opportunities for participation by PM TBD <br /> MBE/WBE subcontractors <br /> 2 Obtain cost estimates from Stantec pre- PM or Field Staff Drilling and locating Subcontractors used must be Stantec pre-qualified and <br /> qualified drilling and locating subcontractors subs(TBD) applicable task orders must be used. <br /> 3 Select contractors and execute PM Drilling and locating <br /> contract/task orders subs TBD <br /> 4 Schedule contractors PM or Field Staff Drilling and locating Start date will depend on contractor availability and site <br /> subs TBD access considerations. <br /> 5 Order lab bottles Field staff Pace National Labs <br /> 6 Order rental field a ui meni Field staff Pine Environmenta Rent PID and survey equipment,if needed <br /> Pre-Field 2-3 weeks Review access agreement and provide notification as <br /> 7 Coordinate access w/property owner(s), Field staff appropriate,and make arrangements if necessary for access <br /> obtain drilling permits if needed to locked or gated locations.Obtain permits,if required,from <br /> San Joaquin County Environmental Health Depertment. <br /> 8 Confirm location for temporary storage of Field staff Only limited waste is anticipated(i.e.,one 55-gallon drum(s)o <br /> investigative wastes if necessa soil cuttings,one drum of equipment rinsate <br /> 9 Mark borehole locations and open dig alert Field staff Mark work locations in white paint and open one-call dig <br /> notification with USA North <br /> 10 Private utility clearance and geophysical PM or Field Staff Locating sub(TBD) Retain services of subcontractor to conduct geophysical <br /> survey surveyfor UST and clear proposed drilling locations <br /> 11 Complete and Review Health&Safety Plan Field staff&PM <br /> 12 Mobilize to site Field staff <br /> 13 Site health&safety"tailgate"meeting Field staff Tailgate meeting should include all personnel onsib <br /> 14 <br /> Photograph/document existing conditions in Field staff Photograph all areas where pavement or landscaped areas <br /> areas to be disturbed may be impacted by sampling activities/e ui men <br /> Review results with subcontractor and verify that utilities have <br /> 15 Review geophysical survey results. Field staff been cleared or complete utility locating.Assess vicinity of <br /> former UST for potential voids/evidence of a tank, <br /> 16 Perform soil sampling with geoprobe,install Field staff Drilling sub(TBD) <br /> vapor probes in select boreholes, <br /> 17 Field screen soil samples with PID Field staff Prior to initial measurements,calibrate instrument per <br /> manufacturer's instructions <br /> Measure/survey locations for all Measure locations for all sample locations relative to two or <br /> 18 borings/probes Field staff more local"landmarks"(building corners,utility poles,etc.)or <br /> use hand-held GPS locating equipment <br /> 19 Store investigative wastes in secure Field staff <br /> Field 3 days location <br /> Investigation 20 Backfill borings with bentonite or grout,as Field staff Drilling sub(TBD) <br /> specified by permh <br /> 21 Verify that all required CA/QC samples Field staff <br /> have been collected <br /> 22 Prepare soil and vapor samples for Field staff Verify shipping method and sample hold times. <br /> shi ment to laborato <br /> 23 1 Verify that all samples have been included Field staff <br /> in coolers <br /> 24 Complete chain of custody form and ship Field staff Pace National Labs Request EQUIS compatible data set be provided with sample <br /> sam le coolers to laboratory results <br /> 25 Photograph/document conditions upon Field staff <br /> completion of field work <br /> 26 Confirm receipt of samples by laborato Field staff Pace National Labs <br /> 27 Scan all field notes/forms and save on Field staff <br /> network <br /> 28 Complete all required field forms Field staff <br /> Upon receipt of laboratory data,coordinate <br /> 29 entry of data into the EQUIIS data PM <br /> mans ement tool <br /> 30 Complete initial evaluation and validation of PM <br /> soil and soil gas data <br /> 31 Provide update to City of Lodi on initial PM <br /> findings <br /> 32 Prepare draft figures and tables for re orl Field staff/PM <br /> Data Analysis/ 33 Prepare draft text for report Field staff/PM <br /> Reporting 4 weeks 34 Complete Stantec CIA technical revie�% CIA reviewers <br /> 35 Complete Stantec CIA independent reviem CIA reviewers <br /> 36 Revise report and compile Draft Report for Field/admin <br /> submittal to City of Lodi staff/PM <br /> 37 Revise report based on comments(if Field staff/PM <br /> required) <br /> 38 Submit Final Report to City of Lodi and EPA Admin staff/PM <br /> 39 Update site information in ACRES IPM <br /> ACRES=Assessment,Cleanup,and Redevelopment Exchange Systen PM=project manager <br /> EPA=Environmental Protection AgencN CIA=quality assurance <br /> GPS=global positioning satellite QA/QC=quality assurance/quality contro <br /> MBE=minority-owned business enterprise TBD=to be determined <br /> PID=photoionization detector WBE=women-owned business enterprise <br />