ATTACHMENT 4 <br /> STANDARD OPERATING PROCEDURES FOR <br /> SOIL BORING AND WELL CONSTRUCTION PROCEDURES <br /> Revised 06/30/02 <br /> 1. Pre-Drilling Protocol <br /> Prior to the start of drilling, necessary permits, site access agreements, and/or encroachment <br /> permits are obtained "As-built"drawings are obtained if possible At least 48 hours prior to <br /> dnlling, Underground Service Alert or an equivalent utility notification service is notified A <br /> geophysical survey may be conducted to locate subsurface utilities by either Consultant or other <br /> outside third party geophysical contractors <br /> Site plans and/or"as-built" drawings are compared to actual conditions observed at the site The <br /> property owner/retailer is interviewed to gain information about locations of former UST systems <br /> including dispensers, product lines, and vent lines A visual inspection is made of the locations of <br /> the existing UST system, and scars and patches in pavement are noted The emergency shut-off <br /> switch is located for safety purposes The critical zone, which is defined as 10 feet from any part <br /> of the UST system, is identified, and any proposed drilling locations within the critical zone <br /> may be subject to special hole clearance techniques Drilling locations within the critical zone are <br /> avoided if possible <br /> Notifications are made at least 2 weeks in advance of drilling to the property owner, client <br /> representative, on-site facility manager, regulatory agency, and/or other appropriate parties <br /> A site-specific, worker health and safety plan for the site is available on site at all times during <br /> drilling activities Prior to commencing drilling, a health and safety meeting is held among all <br /> on-site personnel involved in the drilling operation, including subcontractors and visitors, and is <br /> documented with a health and safety meeting sign-in form A traffic control plan is developed <br /> prior to the start of any dulling activities for both on-site and off-site drilling operations The <br /> emergency shut-off switch for the service station is located prior to the start of the drilling <br /> activities A fire extinguisher and "No Smoking" signs (and Proposition 65 signs in California) <br /> are present at the site prior to the start of the drilling activities) <br /> The first drilling location is the one located furthest from any suspected underground <br /> improvements in order to determine the natural subsurface conditions, to be able to better <br /> recognize fill conditions, and to prevent cross contamination For monitoring wells, a 2 x 2-foot <br /> square or 2-foot diameter circle is the minimum removal For soil borings and push-type <br /> samplers, the minimum pavement removal is 8-inches When pea gravel, sand, or other <br /> non-indigenous material is encountered, the drilling location will be abandoned unless the <br /> absence of subsurface facilities can be demonstrated and client approval to proceed is obtained If <br /> hole clearance activities are conducted prior to the actual day of drilling, the clearance holes are <br /> Matn\D\Environmental\Parmar Texaco\Workplan\042003 wpd 1 <br />