Laserfiche WebLink
Revised Traffic Impact Study March 27,2008 — <br /> Proposed CEMEX Mining Site Page 17 <br /> The intersection is expected to operate at a level of service F in the year 2025 even without the <br /> proposed Project. Haul Route 1 is not expected to create additional significant impacts in the year <br /> 2025. However,Haul Route 3 would contribute to the cumulative year 2025 impacts. <br /> To mitigate the impacts created by Haul Route 3 on opening day, all-way stop control would be <br /> required. However, all-way stop control should not be installed unless warrants are satisfied after <br /> the Project begins operating. Since Haul Route 3 is expected to be an alternate route, it is unlikely _ <br /> that warrants for all-way stop control will be met on a long-term basis. Therefore, this impact may <br /> be considered adverse but not significant. <br /> To mitigate the cumulative impacts with Haul Route 3 in the year 2025, all-way stop control with — <br /> construction of a westbound left-tum lane is expected to be required. As an alternative to mitigating <br /> cumulative year 2025 conditions, the Project may be conditioned to eliminate Haul Route 3 after the <br /> pending construction of the Bird Road/ SR 132 interchange, at which time only Haul Route 1 would — <br /> be allowable. <br /> Intersection of Bird Road and SR 132 _ <br /> The intersection is currently operating at unacceptable levels of service. Construction of the pending <br /> interchange appears to be warranted and is expected to mitigate the operation of the intersection to <br /> acceptable levels of service through the year 2025. The Project may be required to contribute an — <br /> equitable share of the cost of the interchange or pay established development fees. <br /> Intersection of Koster Road and SR 132 <br /> The intersection is currently operating at unacceptable levels of service. Neither of the proposed <br /> haul routes will utilize Koster Road at this intersection. Therefore, the Project will not create new <br /> turning movements and will only result in new through movements on SR 132. Project-specific _ <br /> significant impacts are not identified at the intersection. <br /> Intersection of SR 132 and Vernalis Road (Connector to SR 33) <br /> The analyses indicate that the intersection is currently operating at a level of service F. The existing <br /> substandard level of service is primarily a result of the difficulty experienced by vehicles attempting <br /> to tum left across traffic on SR 132. The proposed haul routes do not propose left turns at the _ <br /> intersection. Haul Route 1 will result only in additional through movements on SR 132 and Haul <br /> Route 3 will result only in right-tum movements and through movements at the intersection. <br /> Therefore, Project-specific significant impacts are not identified. _ <br /> Intersection of Welty Road and SR 132 <br /> The analyses indicate that the intersection is currently operating at a level of service F. The existing <br /> substandard level of service is primarily a result of the difficulty experienced by vehicles attempting _ <br /> to tum left across traffic on SR 132. Haul Route 1 will result only in additional through movements <br /> on SR 132 and Haul Route 3 will result only in right-turn movements and through movements at the <br /> intersection. Therefore,Project-specific significant impacts are not identified. <br /> Intersection of McCracken Road and SR 132 <br /> The analyses indicate that the intersection is currently operating at a level of service F. The existing — <br /> substandard level of service is primarily a result of the difficulty experienced by vehicles attempting <br /> to tum left or proceed through across traffic on SR 132. The proposed Project will result only in <br /> additional through movements on SR 132. Therefore, Project-specific significant impacts are not <br /> identified. <br />