1 <br /> 6.0 SCHEDULE <br /> 1 The work schedule will be determined upon approval of this work plan by the EHD and <br /> 1 the availability of the excavation contractor (Del-Tech). Lee & Pierce will ensure that <br /> Underground Service Alert will be notified at least 48 hours prior to the start of field work. <br /> 1 The proposed schedule includes: <br /> 1 1. Excavation and stockpiling activities. 3 working dates. <br /> 1 2. Secure soil samples from excavation floor and sidewalls and stockpiled material <br /> and transmit under chain of custody to Argon to be analyzed for constituents of <br /> 1 concern. 1 day during excavation activities. <br /> 3. Removal excavated soil to west side of building to establish soil pile. Completed <br /> 1 during excavation activities. <br /> 4. Place and compact fill material. 1-2 working days. <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> fSOIL REMOVAL WORKPLAN [041131111 6 LEE&PIERCE INC.[JOB#107591 <br /> 1 <br />