Primary Piping System Installation <br /> The normal recommended procedure is to conduct Avoid personal contact with the piping system while <br /> a hydrostatic cyclic pressure test. The piping system is it is pressurized during testing except for actual checking <br /> subjected to 10 pressurization cycles at 11/2 times the of the joints for leaks. Absolutely no one should be in <br /> anticipated or design operating pressure. NOTE: For low the trench while the pipe is being initially pressurized for <br /> pressure applications, it is best to use the pressure rating leak testing. Notify all site personnel before beginning <br /> of the pipe as the design operating pressure, i.e. test at the testing procedure. <br /> 11/2 times the cyclic rating. The test pressure should not <br /> exceed 1 1/2 times the maximum rated operating pressure Do not straddle the pipe during testing or while checking <br /> for the lowest rated element in the system. Pressure the piping system for possible leaks. <br /> is then kept on the system for 1-8 hours while the line is <br /> inspected for leaks. While the pipe is being checked for leaks,do not stand at <br /> the end of the piping system or where it changes <br /> Air Test Procedures and Safety Precautions(') directions. <br /> TESTING WITH AIR OR GAS IS EXTREMELY <br /> DANGEROUS AND SHOULD NOT BE DONE. CONSULT CAUTION: Failure to strictly follow these instructions <br /> YOUR FGS REPRESENTATIVE OR CALL 501-618-2243 can result in serious personal injury, death, and/or <br /> FOR TECHNICAL ASSISTANCE. IF YOU CONTEMPLATE property damage. <br /> EXCEEDING THE RECOMMENDED PRESSURES FOR <br /> THE LOWEST RATED ELEMENT OF THE SYSTEM OR IF • FGS recommends that after the piping has passed the <br /> YOU CONTEMPLATE USING AIR OR GAS IN SPITE OF 50 psig(0.345 MPa)pressure test,the contractor should <br /> THE WARNING, REVIEW ALL SAFETY PRECAUTIONS reduce the product line pressure to a pressure of not <br /> BEFORE STARTING THE TEST. more than 25 psig(0.172 MPa)and maintain this pressure <br /> until all paving has been completed. Leave pressure <br /> If testing with air or gas is required or requested to be gauge on each line for inspection. The contractor should <br /> performed,the following testing procedures and precautions check the gauge daily to verify the pipe is holding <br /> must be followed. As in any system where pressure is pressure. <br /> employed, adequate safety precautions must be exercised. <br /> EXERCISE DUE CARE IN INSTALLING AND TESTING If a leak is encountered during the test procedure, <br /> THE PIPING SYSTEM. immediately release all pressure in the piping system and <br /> refer to pages 14-15 for proper repair procedures. Upon <br /> • Visually inspect all bonded joints for proper insertion completing any necessary repairs to the piping system, <br /> and adhesive cure prior to pressurizing the piping follow the proper testing sequence and verity the system's <br /> system.A gap between the adhesive bead and the fitting integrity. <br /> shoulder indicates that the possibility of joint failure <br /> exists. Make any necessary repairs before pressurizing Vacuum or Inert Gas Test Procedures <br /> the piping system. See page 12 for potential causes of Testing with vacuum and/or pressurized inert gases have <br /> joint failure. been successfully used with FGS Smith Fibercast piping <br /> systems. Although helium testing in a closed atmosphere <br /> • Check the integrity of the joints by pressurizing the and at measured levels is useful, testing in the field with <br /> system to 25 psig(0.172 MPa)and holding the pressure helium has shown inconsistencies when attempting to <br /> for a minimum of one minute. Soap all joints to test for identify leak location. <br /> leaks. <br /> 0)Do not use these testing procedures and safety precautions for FGS <br /> • If there are no leaks, raise the line pressure in the Smith Fibercast RED THREAD IIA secondary containment piping systems. <br /> See page 23 of this manual for testing procedures for secondary contain- <br /> system to a maximum of 50 psig (0.345 MPa). Again, ment piping systems. <br /> hold the pressure for at least one minute and soap all <br /> joints to check for leaks. <br /> • As serious personal injury or death can result, the pipe <br /> inspector should take precautions for his/her personal <br /> safety and protection against flying debris and also <br /> against the whipping action of the pipe that can result <br /> from the sudden release of stored energy. Goggles <br /> should be worn to protect against flying debris. <br /> 13 <br />