C <br />DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 016 <br />Project Number: 11-101-01 Date: Tuesday 06/02/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: T. Sathees <br />Contractor: R J Gordon Construction, Inc. <br />Weather: Clear Wind: 0-10 mph. <br />Temperature: Agprox. range 60-85 F Other: <br />The contractor worked from 7:00 am to 5:30 pm. <br />Excavation: 7:00 am to 5:30 pm. Up to (1) CAT D6 and (1) CAT D8 dozers with ripper attachments assisted up to (4) CAT 627 <br />and (2) CAT 637 scrapers load material from the excavation along north and east sides of the cell. The soil was hauled and <br />stockpiled at South Stockpile 1 for use as Foundation layer, at South Stockpile 2 for use as Operations layer soil, and to <br />Earthfill construction along south side of the cell. The soil was hauled on an approximate 5 -min cycle. (1) CAT 637 scraper <br />went idle after mid-day. <br />(1) CAT 14H motorgrader and (1) CAT D6 dozer (with slope board attachment) part time trimmed the upper slopes along <br />north side of the cell. <br />North West Stockpile: No activity was observed. <br />South Stockpile 1 (Foundation): 7:00 am to 5:30 pm. The scrapers hauled the fine-grained materials from slopes along <br />north side of the cell to the South Stockpile 1 for use as Foundation layer soil. One composite sample was obtained, and the <br />fines content was 36 % of the portion finer that 3/8 -inch. (1) CAT 14H motorgrader and (1) CAT D6 dozer were observed <br />part time spreading and grading the soil in the Stockpile fill areas, and maintaining haul roads. (1) CAT 621 water pull was <br />used to maintain stockpile fill areas, and haul roads. <br />South Stockpile 2 (Operations): 7:00 am to 5:30 pm. The scrapers hauled the generally sandy materials from upper slopes <br />along northeast and east sides of the cell to the South Stockpile 2 for use as Operations layer soil. One composite sample was <br />obtained, and the fines content was 19 % of the portion finer that 3/8 -inch. (1) CAT 14H motorgrader and (1) CAT D6 dozer <br />were observed part time spreading and grading the soil in the Stockpile fill areas, and maintaining haul roads. (1) CAT 621 <br />water pull was used to maintain stockpile fill areas, and haul roads. <br />Access Road Embankment Fill (Earthfill): No activity was observed. <br />Subgrade Earthfill: 7:00 pm to 5:30 pm. The scrapers hauled the soil from the excavation areas and placed Earthfill along <br />south side of the cell. (1) CAT 621 water pull moisture -conditioned the Earthfill. (1) CAT 825 compactor was used to break <br />the big clods and to compact the Earthfill. Density testing on the Earthfill indicated compliance with the specifications. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T dozer, (1) CAT D6R dozer (with slope board) (1) CAT 621G water pull, <br />(4) CAT 627 scrapers, (3) CAT 637 scrapers, (1) 14H motorgrader, (1) CAT 825H compactor <br />Problems/Resolutions. <br />Visitors: M. Raub <br />Reviewed By: M. Raub <br />