DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 017 <br />Project Number: 11-101-01 Date: Wednesday 06/03/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: T. Sathees <br />Contractor: R J Gordon Construction, Inc. <br />Weather: Clear Wind: 0-10 mph. <br />Temperature: Approx. range 60-85 F Other: <br />The contractor worked from 7:00 am to 5:30 pm. <br />Excavation: 7:00 am to 5:30 pm. Up to (2) CAT D6 and (1) CAT D8 dozers with ripper attachments assisted up to (4) CAT 627 <br />and (2) CAT 637 scrapers load material from the excavation along north and east sides of the cell. The soil was hauled and <br />stockpiled at South Stockpile 2 for use as Operations layer soil, and to Earthfill construction along south side of the cell. The <br />soil was hauled on an approximate 5 -min cycle. <br />(1) CAT 14H motorgrader and (1) CAT D6 dozer (with slope board attachment) part time trimmed the upper slopes along <br />north and east sides of the cell. <br />North West Stockpile: No activity was observed. <br />South Stockpile 1 (Foundation): No activity was observed. <br />South Stockpile 2 (Operations): 7:00 am to 5:30 pm. The scrapers hauled the generally sandy materials from upper slopes <br />along north and east sides of the cell to the South Stockpile 2 for use as Operations layer soil. Two composite samples were <br />obtained, and the fines content were 10 and 15 % of the portion finer that 3/8 -inch. (1) CAT 14H motorgrader and (1) CAT <br />D6 dozer were observed part time spreading and grading the soil in the Stockpile fill areas, and maintaining haul roads. (1) <br />CAT 621 water pull was used to maintain stockpile fill areas and haul roads. <br />Access Road Embankment Fill (Earthfill): No activity was observed. <br />Subgrade Earthfill: 7:00 pm to 2:30 pm. The scrapers hauled the soil from the excavation areas and placed Earthfill along <br />south side of the cell. (1) CAT 621water pull moisture -conditioned the Earthfill. (1) CAT 825 compactor was used to break the <br />big clods and to compact the Earthfill. One sample was obtained and maximum density test was conducted to help select the <br />appropriate compaction cure. Density testing on the Earthfill indicated compliance with the specifications. <br />One backup water truck was delivered to the site. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T dozer, (1) CAT D6R dozer (with slope board) (1) CAT 621G water pull, <br />(4) CAT 627 scrapers, (3) CAT 637 scrapers, (1) 14H motorgrader, (1) CAT 825H compactor, (1) water truck <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />