C <br />�7� <br />DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 008 <br />Project Number: 11-101-01 Date: Wednesday 05/20/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: T. Sathees <br />Contractor: R J Gordon Construction, Inc. <br />Weather: Partly cloudy Wind: 0-10 mph. <br />Temperature: A22rox. range 55-85 F Other: <br />The contractor worked from 7:00 am to 5:30 pm. <br />Excavation: 7:00 am to 3:30 pm. Up to (1) CAT D6 and (1) CAT D8 dozers with ripper attachments assisted up to (4) CAT 627 <br />and (2) CAT 637 scrapers load material from the excavation along north side of the cell. The soil was hauled and stockpiled at <br />North West Stockpile for use as daily cover for current landfill operations and to Earthfill construction below the Access Road <br />at the west side of the work area. The soil was hauled on an approximate 5 -min cycle. (1) CAT 14H motorgrader was <br />observed fine grading part time on the upper portion of the north slopes. <br />In the morning, the CAT D6 dozer also assisted up to (2) CAT (637) scrapers load material from the excavation along west <br />side of the cell. The soil was hauled and placed as Earthfill below Access Road at west side of the cell. <br />3:30 pm to 5:30 pm. Scrapers were idle. The CAT D6 and D8 dozers, CAT 14H motorgrader, and CAT 825 compactor started <br />ripping and breaking the large clods at the existing subgrade at south side of the cell, where Earthfill is required to bring the <br />subgrade to bottom of Foundation layer. The CAT 621 water pull moisture -conditioned the surface to assist the process <br />North West Stockpile: 7:00 am to 3:30 pm. (1) CAT 14H motorgrader was observed spreading and grading the soil in the <br />Stockpile fill areas, maintaining haul roads. (1) CAT 621 water pull was used to maintain fill areas, haul roads, and excavation <br />areas. <br />South Stockpile (Fdn. Stk.): No activity was observed. One sample was tested on previously stockpiled material and the <br />fines content of the stockpiled material was 38 percent of the portion finer that 3/8 -inch. <br />Access Road Embankment Fill (Earthfill): 7:00 am to 3:30 pm. (2) CAT 627 scrapers continued hauled the soil from the <br />excavation areas and placed thin lifts. The soil appeared to be mixture of brown silty/clayey sand and grey sand. (1) CAT 621 <br />water pull moisture -conditioned the Earthfill. The CAT 825 compactor was used to compact the Earthfill. Density testing on <br />the Earthfill indicated compliance with the specifications. One sample was obtained from the fill area and maximum density <br />test was conducted to help select the appropriate compaction curve. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T dozer, (1) CAT 621G water pull, (6) CAT 627 scrapers, (3) CAT 637 <br />scrapers, (1) 14H motorgrader, (1) CAT 825H compactor <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />Earth Sclerwes, hw- <br />