C <br />I -- <br />DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 043 <br />Project Number: 14-101-01 Date: Thursday 07/09/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: M. Hu and <br />Contractor: R J Gordon Construction, Inc. <br />Weather: Clear Wind: 0-10 mph. <br />Temperature: Ap2rox. range 70- 85 F Other: <br />The contractor worked from 7:00 am to 4:30 pm. Excavation was shut down at 3:30 and slope preparation continued. <br />Excavation: (1) CAT D6 dozer and (2) CAT 627 dozer graded Basin 1. The material was hauled to the adjacent fill area for the <br />access road, and some loads were taken to Stockpile 3. Only (2) scrapers were used today. (2) CAT 627 scrapers were <br />demobed today. <br />(1) CAT 621 water pull was used to maintain excavations, haul roads and stockpile and fill areas <br />Slope Subgrade Preparation: Up to (6) laborers using hand tools prepared the slope areas. A side boom smooth drum roller <br />was used to roll the north slope. Some of the areas that were rolled complied with the specifications. Some areas needing <br />rework were pointed out to the contractor as typical areas for rework. <br />Access Road: Up to (1) CAT D6 dozer, (1) CAT 14 H motorgrader, (1) CAT 825 compactor, (2) CAT 627 scrapers, (1) CAT 825 <br />compactor continued fill operations for the access road. The lower 1 foot of backfill for the 2 foot over -excavation was tested, <br />one failing test was reworked and retested, another passed the 95% requirement. <br />Foundation Layer: No activity observed today. <br />Sump Construction: No activity observed today. <br />North West Stockpile: No activity was observed. <br />South Stockpile 1 (Foundation): No activity was observed. <br />South Stockpile 2 (Operations): No activity was observed. <br />South Stockpile 3: Some loads from Basin 1 were placed today. <br />Geosynthetics: Deliveries of GCL 32 rolls, HDPE 12 rolls. <br />(2) loads of LCRS rock and (2) loads of Coarse Gravel were delivered today by end dump trucks with pups. <br />Construction of the test pad is scheduled for Monday. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T LGP dozer, (1) CAT D6R dozer (with slope board) (1) CAT 621G water <br />pull, (4) CAT 627 scrapers, (1) 14H motorgrader, (1) CAT 825H compactor, (1) water truck, (1) Hitachi 300 excavator, (1) <br />CAT CS 54B smooth drum roller (vibratory type), (1) CAT TH160B folk lift, (1) CAT side -boom winch smooth drum roller, (1) <br />CAT 430D backhoe. (1) side boom roller <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />w <br />