DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 070 <br />Project Number: 14-101-01 Date: Monday 08/17/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: R. Nogales <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Clear - Hot Wind: 0-10 mph. <br />Tem erature: Approx. range 63- 104 F Other: <br />The contractor worked from 5:00 am to 4:30 pm. <br />Excavation: No activity observed. <br />Access Road: No activity observed. <br />Operations Layer Processing: Screening of Operations Stockpile was performed on Saturday 8/15/2015. AES not on site <br />during screening. (5) Locations within Saturday's screened stockpile were field tested using 1" gradation sieve to measure <br />maximum aggregate size. Observed 100% of material passing 1" Sieve at all (5) locations. (1) Sample collected from Saturday <br />stockpile to run full gradation in field lab. Lab results indicated 100 % Passing 1" Screen. <br />Contractor continued screening of operations stockpile today at 6:00 am. (1) Hyundai 480 excavator, (1) CAT D6 dozer (1) <br />950 M Loader used to perform screening operations. The Hyundai 480 used to load soil from the east end of Stockpile 2 into <br />the Power Screen screening plant. Screened product was stockpiled in a cone using a belt stacker to keep the screened soil <br />separate from unprocessed soil. (1) 950 M Loader used relocate +1" from under belt into separate stockpile. Screening <br />operation ended at 4:00. <br />Operations Layer Placement: (1) D6 LGP Dozer used to spread Operations Layer previously stockpiled on cell floor Friday. <br />Operations layer was placed 2 ft thick over deployed 8 oz/sy geotextile along southern edge of cell working to the north and <br />west. Random samples of Operations layer hand sieved in field with 1" screen during placement. Observed 100% passing 1" <br />screen. <br />Contractor continues to place Operations layer over GDM without Point over Point Survey data. Per contractor, Operations <br />Layer to be potholed down to the geotextile and point over point survey to be performed at that time. <br />Gravel Drainage Material Placement: 10-11 tandem end -dumps were used to import Gravel Drainage Material (GDM) from <br />Cemex Rock Plant until 4:30 pm. Observed 3 ft of GDM between end dumps and underlying geosynthetics. (1) Cat D6 LGP <br />dozer equipped with GPS spread GDM along southeast corner of cell floor this morning beginning at 5:00 am (1) Laborer used <br />to control wrinkles. GDM placement discontinued at approximately 1:00 due to moderate to heavy wrinkles observed in <br />HDPE Liner. GDM import continued, with material being stockpiled on previously deployed GDM. AES QA personnel <br />monitored the placement and verified the depths of the placed LCRS gravel by using a dulled probe. <br />10:30 Observed potentially coarse material in a couple loads of GDM. A sample was collected and field gradation indicated <br />97% passing 3/8" sieve. Contractor was informed that corrective action was needed. Another sample of typical GDM <br />delivered today was collected at 2:30. Field gradation indicates GDM meeting required specifications. <br />Leachate Collection Pipe: No Activity Observed Today <br />24" HDPE Riser Pipe: (1) JD 410 Backhoe, (1) Welding Machine, and (2) laborers welded 24" HDPE Riser pipe. <br />Equipment Onsite: (1) CAT D6T LGP dozer, (2) water trucks, (1) Hitachi 300 excavator, (1) CAT TH160B folk lift, (1) John <br />Deere 410 Backhoe. (1) CAT 623 paddlewheel scraper. (1) Power Screen, (1) Belt Stacker, (1) Hyundai 480LC excavator, (1) <br />CAT D6T dozer, (2) Cat 745 Dump Truck, (1) Cat 950 M Loader <br />Problems/Resolutions. <br />Visitors: Mike Raub <br />Reviewed By: M. Raub <br />�� tI i W�a_� <br />