Laserfiche WebLink
DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 087 <br />Project Number: 14-101-01 Date: Thursday 09/10/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: R. Nogales <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Clear - Hot Wind: 0-15 mph. <br />Temperature: ARprox. range 69- 108 F Other: <br />The contractor worked from 7:00 am to 6:00 pm. <br />Operations Layer Processing: Contractor continued screening of operations stockpile # 3 today at 7:00 am. (1) Hitachi 300 <br />excavator, (1) CAT D6 dozer (1) 950 M Loader used to perform screening operations. The Hitachi 300 used to load soil from <br />Stockpile 3 into the Power Screen screening plant. Screened product was stockpiled in a cone using a belt stacker to keep the <br />screened soil separate from unprocessed soil. (1) 950 M Loader used relocate +1" from under belt into separate stockpile. (1) <br />Sample collected from the stacker belt. Full gradation was performed in the field lab. Lab results indicated 100% Passing 1" <br />Screen. Screening operation ended at 6:00 pm. <br />Operations Layer Placement: (1) Hyundai 480LC loaded (2) Cat 745 Dump Trucks with Screened Operations Layer for <br />placement on cell floor. (1) D6 LGP and (1) D4 Dozer were used on a part time basis to spread Operations layer 2 ft thick over <br />deployed 8 oz/sy geotextile along western and northern edges of the cell. (1) 14M Motor Grader was used to fine grade <br />operations layer. (1) Random samples of Operations layer were hand sieved in field with 1" screen during placement. <br />Placement discontinued at 3:30 pm. <br />Gravel Drainage Material Placement: Import had been completed. No GDM placement or grading was performed today. <br />Geotextile: Great Basin hand sewed previously deployed 8 oz/sy geotextile along western edge of the cell. Great Basin <br />deployed and sewed 8 oz/sy geotextile over previously placed GDM in the middle portion of sump. (2) Laborers were used to <br />hand roll Geotextile into place. (1) Laborer was observed using hand sewing machine to sew seams. <br />Geocomposite: 8 oz Geotextile seams were sewn by Great Basin using hand sewing machine along sides of previously <br />deployed Geocomposite on the Northern Slope. Observed 3ft overlap and nylon ties placed at 6 -inch intervals along the tie in <br />with Area 1. An 8 oz Geotextile cap was placed over nylon ties and heat bonded to existing Geocomposite. <br />Leachate Collection Pipe: Contractor installed remaining balance of Northern Leachate Collection Pipe. Approximately 45 if <br />of 6" perforated HDPE pipe was placed today. (1) John Deere 410 Backhoe operating over completed operations layer soil <br />was used to place coarse gravel over 6" Perforated HDPE Pipe. Coarse gravel and 6" HDPE pipe was wrapped in 8 oz/sy <br />Geotextile. Gravel was measured to be a minimum 1 ft deep and a minimum 4 ft wide. Geotextile was measured to have a 2 ft <br />minimum overlap. <br />Force Main: (1) Hitachi 300 and (2) Laborers were used to excavate portions of 2 ft wide trench for Force Main and electrical <br />conduit. During excavation Hitachi 300 damaged an active 2" condensate line. The damaged line was repaired immediately. <br />Leak Detection: Leak Location Services Inc. on site today to perform leak location survey. Survey not completed today. <br />24" HDPE Riser Pipe and Sump: (1) Hitachi 300 was used to hoist 24" Primary Riser pipe back into position. Riser pipe had <br />slid down slope approximately 4' raising the end of pipe 8" off of sump floor. Observed bottom of 24" Riser pipe resting once <br />again on Sump Floor. <br />Coarse Gravel Placement: (1) Cat 950 M Loader used to place coarse gravel into sump and over ends of 24" HDPE Riser <br />Inspection pipes. Addition gravel needed to reach required Coarse gravel grade. <br />Anchor Trench: Great Basin removed sand bags and cut geosynthetics square to back of Eastern Anchor Trench. RJG used (1) <br />Loader and (1) Water truck to moisture condition and place Operation Layer soil in southernmost portion of Anchor Trench. <br />(2) Laborers hand graded operation layer and applied compactive effort using Mechanical Tamper. Field density testing <br />indicated 90% relative com action and +Z- 3% of optimum moisture content was achieved. <br />Equipment Onsite:, (1) CAT D6T LGP dozer, (2) water trucks, (1) Hitachi 300 excavator, (1) CAT TH160B folk lift, (1) John <br />Deere 410 Backhoe. (1) CAT 623 paddlewheel scraper. (1) Power Screen, (1) Belt Stacker, (1) Hyundai 480LC excavator, (1) <br />CAT D6T dozer, (2) Cat 745 Dump Truck, (1) Cat 950 M Loader (1) CAT D4 Dozer (1) 14M Motor Grader <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />Adtwnrad <br />• - F.ar th NCI tnc <br />