Laserfiche WebLink
5-24-99 Weeldy Field Report Job No. 986011.0,' <br /> WFR No.3 VECTOR ENGINEERING,. INC. Page No. <br /> Thursday May 27, 1999 <br /> Guinn—Guinn continues to excavate the material from the southern slope of Cell WMU D-99 utilizing 1-623/2-633 <br /> paddle wheel scrapers. CQA informed Guinn to sort the sandy material unsuitable for the clay mix in one stockpile and <br /> the clean clayey material in the clay mix stockpile.The water truck continues to perform dust control and is <br /> moisturizing the stockpile as material is being placed. Guinn continues to clean the clay tie in along cell WMU D-98. <br /> Allied—Allied continues to work on subgrade preparation on the west slope of the Ashpit.Allied is utilizing an <br /> excavator to load 2 rock tracks to haul material from WMU B to the west slope. The material is being spread and track <br /> walked by a D4 and a D8 in approximately 8"loose lifts. Allied continues to place garbage and daily cover material as <br /> fill on the southeastern slope. Allied is trimming the top deck to grade. <br /> Friday May 28, 1999 <br /> Guinn—Guinn continues to excavate the material from the south slope and the eastern toe of slope of Cell WMU D-99. <br /> Guinn continues to sort the material suitable for the clay mix in one stockpile and the questionable material in a <br /> separate stockpile. Guinn placed.75' of on site clayey material and.25' of Narco clay on the clay mixing pad area for <br /> Griffin to mix on Monday. <br /> Allied-Allied continues to place garbage and daily cover material as fill on the southeastern slope. Allied is also <br /> constructing the anchor trench area on the southeastern slope. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: V5 <br />