Laserfiche WebLink
6-28-99 Weekly Field Report Job No. 986011.0: <br /> WFR No.9 VECTOR ENGINEERING, INC. Page No. <br /> Wednesday June 30, 1999 <br /> GSE—GSE started deployment of the GCL on the eastern slope of cell WMU D-99 below bench#1. A total <br /> of 18 panels were placed with approximately 12,353.5ft2 being deployed. GSE placed 11 panels of <br /> geomembrane over the GCL totaling approximately 10950f 2 being deployed. All panels were seamed and <br /> anchored. No airtests were performed due to the excessively high heat. GSE unloaded 3 loads of GCL <br /> delivered to the site today. <br /> Thursday July 1, 1999 <br /> Guinn performed clean up and some detail work on the southern slope of cell WMU D-99. Guinn worked on <br /> grading the access ramp entering from the Northwest of cell WMU D-99. <br /> GSE deployed geomembrane on the cell floor from the tie in to cell WMU D-98 towards the south. A total of <br /> 20 panels were placed with approximately 99,753ft of geomembrane being deployed. All panels were <br /> seamed and airtested. GSE unloaded 1 load of GCL delivered to the site today. GSE performed several <br /> repairs on the destruct areas and panel air test points. <br /> Friday July 2, 1999 <br /> Guinn had 3 laborers and foreman placing and welding 50' sections together of HDPE pipe on the cell floor <br /> in the East West LCRS channel. Guinn welded 9 sections of pipe together. <br /> GSE had 10 more crew arrive on site. GSE deployed geomembrane on the cell floor, sump area and the <br /> eastern slope from the 2nd bench down to the I"bench. GSE completed placement on the cell floor except <br /> for the southern tie in to the ashpit. GSE completed placement of the GCL and liner in the sump area. GSE <br /> squared up GCL and liner and made the tie in from the 2nd bench above the cell on the eastern slope down to <br /> the lst bench. A total of 20 panels were placed with approximately 00000f12 of geomembrane being <br /> deployed. All panels were seamed and airtested. GSE performed repairs on all of the geomembrane material <br /> placed. GSE pulled samples in 10' intervals off of each end of the failing destruct and tested them prior to <br /> removing destruct samples for testing by CQA. Destruct 12A was pulled 20 feet to the west of#12 and 12B <br /> was pulled 10' East of destruct 12and both passed the required specifications. <br /> Saturday July 3, 1999 <br /> GSE vacuum tested all repairs made on the cell floor and the 1st bench above the cell floors eastern slope. <br /> GSE pulled destructs for testing by CQA on the slope from the 2nd bench down to the l st bench. GSE <br /> completed detail work on the cell floor and sump areas. GSE stagged rolls of bentomat on the 3d bench <br /> above the cell floor on the eastern slope. GSE placed GCL on the slope below the 2°d bench down to the 1st <br /> bench. A total of 23 panels were placed with approximately 27159ft2. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: J5 <br /> I "=== _j <br />