7-12-99 Weeldy Field Report Job No. 986011.0: <br /> WM No.10 VECTOR ENGINEERING, INC. page No. 2/2— <br /> Wednesday <br /> /ZWednesday July 14, 1999 <br /> GSE: GSE deployed GCL and geomembrane on the top of the Ashpit and on the eastern slope of the Ashpit. <br /> GSE deployed 23 panels of GCL withap roximately 25,344fl and 5 panels of HDT geomembrane on the <br /> top of the Ashpit with a total of 10,672 GSE deployed 10 panels of HST geomembrane on the eastern <br /> slope of the Ashpit with approximately 16,428ft2. <br /> Thursday July 15, 1999 <br /> Guinn: The tank for the sump arrived on site. Guinn continued to import and grade the GDM utilizing the <br /> 134H and the D5M Guinn continues to place geotextile and operation layer material over the approved <br /> GDM. Guinn utilized the grader to partially backfill the eastern slope anchor trench_Guinn compacted the <br /> damaged subgrade on the northwest comer of the Ashpit utilized by GSE for access. <br /> GSE: GSE deployed GCL and geomembrane on the eastern slope of the Ashpit and between the Ashpit and <br /> the eastern slope of cell WMU D-99. GSE deployed 13 panels of GCL with approximately 9,7671 and 6 <br /> panels of HST geomembrane with a total of 8,6241. <br /> Friday July 16, 1999 <br /> Guinn:Guinn continued to import and grade the GDM utilizing the 134H and the DSM. Guinn continues to <br /> place geotextile and operation layer material over the approved GDM. Guinn placed the drainage burrito in <br /> the LCRS running East to West. Guinn placed material that had been rejected due to the amount of fines was <br /> out of specifications for the project. While getting a bucket full of the rejected material the loader also <br /> picked up some muddy rock. CQA informede meadows that even though Guinn hed down the <br /> stockpile with the water truck prior approval testing of the material before Guinn could <br /> place it. <br /> GSE:GSE deployed GCL and geomembrane on the northern slope of the Ashpit. GSE deployed 34 panels <br /> of GCL with approximately 44,1401 and 18 panels of HST geomembrane with a total of 43,53812. <br /> Saturday July 17, 1999 <br /> GSE:GSE deployed GCL and geomembrane between the Ashpit and the eastern slope of cell WMU D-99. <br /> GSE deployed 16 panels of GCL with approximately 3,3821 and 6 panels of HST geomembrane with a total <br /> of 4,40412. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era. Reviewed by: <br />