Laserfiche WebLink
7-19-99 Weekly Field Report Job No. 986011.0 <br /> VIER No,11 VECTOR ENGINEERING, INC. Page No.212- <br /> Wednesday <br /> 2Wednesday July 21, 1999 <br /> GSE: GSE deployed geocomposite from the northern slope of the Ashpit down over the southern slope of <br /> cell WMU D-99 down to the cell floor. A total of 42panels were placed with approximately 59,287.5ft2. <br /> Thursday July 22, 1999 <br /> Guinn: Guinn continues to place geotextile and operation layer material over the approved GDM. Guinn <br /> placed a 3' extension onto the 6"LCRS pipe running from the west towards the east so the pipe would lay in <br /> the bottom of the V ditch on the eastern edge of the cell. Guinn reconnected the 6"LCRS pipe tying into cell <br /> WMU D-98 in the eastern V channel. Guinn excavated and back-filled the anchor trench across the southern <br /> roadway. Guinn excavated the anchor trench on the southem bench in the southwest corner of cell WMU D- <br /> 99. <br /> GSE: GSE completed deployment of the geocomposite from the southern slope of cell WMU D-99 down to <br /> the cell floor. A total of 11 panels were placed with approximately 7.592.5fl. GSE cleaned up the site of <br /> garbage. GSE pulled back and placed the liner in anchor trenches as Guinn excavated them. GSE left the site <br /> today. <br /> Friday July 23, 1999 <br /> Guinn: Guinn continues to place geotextile and operation layer material over the approved GDM. Guinn <br /> back-filled and compacted the anchor trench on the southern bench in the southwest corner of cell WMU D- <br /> 99. Guinn placedgeotextile around the sump tank and compactedoperations layer material over the sump <br /> area. Guinn placed a lift of subgrade material in the anchor trenches on the western slope f the Ashpit. <br /> He Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: tf j <br />