7-26-99 Weekly Field Report Job No. 986011.0: <br /> WFR No.12 VECTOR ENGINEERING,, INC. Page No. <br /> Project Name: Client Or Owner: 12 <br /> Forward Land Fill Allied Waste <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Manteca,CA Butch Stefan,Jr 7-26-99 TO 8-1-99 Mon-Sun <br /> General Contractor: Liner Contractor P-j. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Grading Contractor Superintendent Or Foreman: <br /> Duane Meadows William Geary <br /> Source And Description Of Fill Material: Weather: CQA Technician/Technician: <br /> Clear Warm FRANK DELL ERA <br /> Equipment used: <br /> Guinn: 140G Grader,3-633/1-623 Paddle Wheels,D411 Cat Dozer,DSH Cat Dozer,320L Cat Excavator,966D Cat loader,Water <br /> Tucl CS 563C Cat Smooth Drum Roller. <br /> NOTES(Describe work compkited during the day,any problems and their solutions): <br /> Monday July 26, 1999 <br /> Guinn: Guinn continues to spread the GDM on the southern and eastern edge of the cell floor. Guinn <br /> backfilled and compacted a portion of the anchor trench on the western edge of the Ashpit. Guinn placed <br /> 400' of perforated 3"pipe and the coarse gravel material in the subdrain on the south slope of the Ashpit. <br /> Guinn utilized wheel barrows to place the gravel in the subdrain. <br /> Tuesday July 27, 1999 <br /> Guinn: Guinn continues to spread the GDM with the D4M on the southern edge of the cell floor. Guinn <br /> placed geotextile over the portions of approved GDM on the eastern edge of the cell floor. Guinn then placed <br /> operations layer material on the eastern edge of the cell floor. Guinn ran out of geotextile material today.ile. <br /> Guinn completed placement of the 3"pipe by placing 40' of solid pipe on the southwestern edge of the <br /> Ashpit geomembrane down to the V channel. Guinn started placement of the vegetative cover on the south <br /> slope of the Ashpit. Guinn placed material from the.earthfill stockpile on the access road and material from <br /> the leachate impoundment on the slope. <br /> Wednesday July 28, 1999 <br /> Guinn: Guinn continues to import and spread the GDM with the D4M on the eastern and southern edge of <br /> the cell floor. Guinn continued to place vegetative cover material on the south slope of the Ashpit. Guinn <br /> placed material from the earthfill stockpile. The material from the leachate impoundment was found to be <br /> unsuitable for fill due to wooded debris in it. Guinn excavated the top 2' of the leachate impoundment and <br /> the material cleaned up. Guinn then placed the impoundment material for vegetative cover material. Guinn <br /> placed vegetative cover over the plywood on the southwest Ashpit anchor trench prior to placing the <br /> protective geotextile under the plywood. Allied had some rolls of geotextile in a storage locker that Guinn utilized <br /> for the protective layer at the anchor trenches. <br /> Thursday July 29, 1999 <br /> Guinn: Guinn continues to spread the vegetative cover material on the south slope of the Ashpit. Guinn <br /> started to place the bench material starting from the western edge of the 1'bench to the south of cell WMU <br /> D-99. Guinn continues to utilize the material from the earthfill stockpile as vegetative and bench material. <br /> Guinn is excavating the leachate impoundment pond area and stockpiling the wooded material in Allieds <br /> stockpile. <br /> [File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: <br />