8-23-99 Weekly Field Report Job No. 986011.0; <br /> WFR No.16 VECTOR ENGINEERING, INC.. Page No. 2/z <br /> GSE deployed a total of 26 panels of 60mi1 geomembrane for the primary liner system in the leachate <br /> impoundment pond totaling approximately 23,967.5ft2. GSE flipped the smooth/textured geomembrane over <br /> with the textured side up so the warranty would not be voided (PER Bill Geary). GSE started to make repairs <br /> today after all seams were airtested. CQA pulled 4 destructs with DS-5p failing. CQA informed GSE who cut <br /> DS—5p A and DS-5p B with failing results. GSE will cap strip the seam in Question. Seam 54/57 was the <br /> second seam performed of the day by IG 2040 so CQA and GSE pulled sample DS-6p from the third seam <br /> welded by IG 2040 with passing results. GSE will cap strip the first seam welded by IG. <br /> Friday August 27, 1999 <br /> GSE: GSE airtested all seams performed today and continued to make repairs to the geomembrane. GSE <br /> tested DS-6p taken from the seam that machine 2040 welded after the failed DS-5p and passed peel and shear <br /> testing. GSE cap stripped all of the seams performed by machine 2040 prior to DS-5p on-6-26.99 due to <br /> samples taken from the seams failed testing. Seams tested after DS-6p passed testing. <br /> Saturday August 28, 1999 <br /> GSE: GSE completed airtesting all seams performed and continued to make repairs to the geomembrane. <br /> GSE installed the boots for the force main drop inlet brackets. GSE started the boots for the lyisometers. GSE <br /> vacuum tested the repairs made to the geomembrane. GSE installed wind vents on the western slope <br /> approximately 1' off of the hinge point at approximately 50' intervals. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: U <br />