Laserfiche WebLink
05/17/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 6 VECTOR ENGINEERING,, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 6 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Manteca,CA Butch St Jr. 5-17-99 Monday <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purd <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy cla Clear Warm FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 140G Grader,2-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator,966D Cat loader,Water Truck.Allied:2- <br /> 300E Cat Rock Trucks, 325 Cat Excavator,D8,D4, 140G Grader, Smooth Drum Roller. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 9 total <br /> Allied Crew: 6 total <br /> Guinn Construction had 2 laborers and the excavator complete exposing the liner tie in and the LCRS pipe. <br /> The water truck is performing dust control all over the haul routes on site. Guinn has the grader grubbing the <br /> clay stockpile area. Guinn is utilizing the D6R to rip the subgrade material on the cell floor and along the <br /> edge of liner. Guinn has the 623 and 2-633 paddle wheels removing the spoils from the excavation along the <br /> liner tie in. Guinn is stockpiling the material to the northwest of cell WMU D-99. Guinn has a laborer hand <br /> shoveling the drainage aggregate off of the liner edge plywood. <br /> Allied is working on subgrade preparation on the eastern slope of the Ashpit. Allied utilized an excavator to <br /> load 2 rock trucks with material from WMU B. The D8 is spreading and track walking the material up the <br /> slope. The water truck is continuously moisture conditioning the subgrade material. The D4 is trimming the <br /> overburden from Friday's placement of subgrade material on the eastern slope of Cell WMU-99 at the liner <br /> tie in. <br /> Vector Engineering,Inc. Guinn informed CQA that the clay import would start on Wednesday. CQA <br /> Observed placement of subgrade material and excavation of liner tie in. Performed density tests on the <br /> subgrade material placed by Allied on the east slope of the Eastern Ashpit with all tests passing results. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: v <br />