05/18/99 Construction Field Report Job No. 986011.0,' <br /> DFR No. 7 VECTOR ENGINEERING, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 7 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Manteca,CA Butch Stefan,Jr. 5-18-99 Tuesda <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy clay Partly Cloudy,Warm FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 14OG Grader,2-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator,966D Cat loader,Water Truck. Allied:2- <br /> 300E Cat Rock Trucks,325 Cat Excavator D8,D4 14OG Grader, Smooth Drum Roller. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 9 total <br /> Allied Crew: 6 total <br /> Guinn Construction is continuing to cut the cell floor down to subgrade finish grade. Guinn utilized 2-633/1- <br /> 623 paddle wheels to excavate and haul the subgrade material to the stockpile area northwest of cell WMU <br /> D-99. Guinn is grading and moisture conditioning the material as it is being stockpiled. Guinn's grade <br /> checker set cut stakes on the cell floor of WMU D-99. Guinn has a laborer hand shoveling the drainage <br /> aggregate off of the liner edge plywood. <br /> Allied to is working on the subgrade preparation on the eastern slope of cell WMU D-99,the southern <br /> slope d top of the Asit. Allied is utilizing 2 rock trucksto haul subgrade material from the WW B cell. <br /> Allied has the water truck moisture conditioning the subgrade material prior to the placement of subsequent <br /> lifts. The subgrade material is being track walked with the D8 and smooth drum rolled for compaction. <br /> Allied started cutting the east slope and bench subgrade material along the liner edge to tie in the east slope <br /> of cell WMU D-99 to the east slope of WMU D-98. <br /> Vector Engineering,Inc. Observed placement and compaction of the subgrade material. CQA performed <br /> density tests on the subgrade material with all tests passing the required specifications. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: �S <br />