Laserfiche WebLink
05/25/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 12 VECTOR ENGINEERING, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 12 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Mant CA Butch Stefan,Jr. 5-25-99 Tuesday <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy clay Partly Cloudy, FRANK DELL-ERA <br /> Warm <br /> Equipment used: <br /> Guinn: 14OG Grader,3-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator, 966D Cat loader,Water Truck.Allied:2- <br /> 300E Cat Rock Trucks,325 Cat Excavator D8,D4 14OG Grader, Smooth Drum Roller. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 9 total <br /> Allied Crew: 6 total <br /> Tim Guinn was on site today. Guinn Construction is cutting on the southern edge of the cell and started to <br /> excavate the access ramp. Guinn has the D6R ripping the subgrade material. The grader is cutting the south <br /> slope 2:1 grade. Guinn utilized 2-633/1-623 paddle wheels to excavate and haul the subgrade material. <br /> Guinn is placing the material suitable for the clay admixture in a stockpile to the northwest of the cell. Guinn <br /> continues to grade and moisture condition the material as it is stockpiled. Guinn utilized the excavator to <br /> locate the leachate pipe to the west of the cell. <br /> Allied Waste is placing garbage and subgrade fill on the southeastern slope of cell WMU D-99. Allied is also <br /> placing subgrade material on the top and western slope of the Ashpit. Allied is utilizing 2 rock trucks to haul <br /> subgrade material from the WMU B.Allied has the water truck moisture conditioning the Ash material prior <br /> to the placement of the subgrade lifts.Allied is utilizing the D8 and the smooth drum for compaction. <br /> Vector Engineering,Inc. Scott Purdy was on site today. CQA attended construction meeting with <br /> representatives from Allied, Guinn and Vector. Observed placement and compaction of the subgrade <br /> material. CQA performed density tests on the subgrade material with several tests failing compaction. CQA <br /> informed Allied. Allied reworked and CQA retested the areas with all tests passing the required <br /> specifications. CQA Informed Guinn that the sample of Coarse Drainage Gravel from Lonestar failed the <br /> sieve analysis for conformance testing with 9.3 %being retained on the 1". Guinn will submit a new sample. <br /> Guinn submitted a sample of GDM for conformance testing. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: 1�r <br />