05/26/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 13 VECTOR ENGINEERING, INC. Page No. 1 <br /> 1 Project Name: Client Or Owner. Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 13 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Mant CA Butch St Jr. 5-26-99 Wednesday <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy 2 U Clear,Warta FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 14OG Grader,3-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator,966D Cat loader,Water Truck.Allied:2- <br /> 300E Cat Rock Trucks, 325 Cat Excavator,D8,D4 14OG Grader,Smooth Drum Roller. <br /> NO'I'11S(]Describe work completed during the day,any problems and their solutions) <br /> Guinn Crew:9 total <br /> Allied Crew: 6 total <br /> Guinn Construction is excavating the southern edge of the cell and the access ramp. Guinn has the D6R <br /> ripping the subgrade material. The grader is cutting the south 2:1 slope and grading on the stockpile. Guinn <br /> utilized 1-623/3-633 paddle wheels to excavate and haul the material to the clay admixture stockpile. Guinn <br /> utilized the excavator to locate and cut the leachate pipe to the south of the southwest access ramp. Guinn <br /> has a laborer with the excavator cleaning and clay tie in by the sump area and the LCRS pipe. <br /> Allied a is placing garbage as subgrade fill on the southeastern slope daily cover material on cell <br /> WMU D-99. Alliedis compacting and trimming the top deck of the Ashpit. Allied is utilizing 2 rock trucks <br /> to haul subgrade material from the WMU B to the west slope for placement as subgrade material. Allied has <br /> the water truck moisture conditioning the subgrade material prior to the placement of the subgrade lifts. <br /> Allied is utilizing the D4 and the D8 to spread and compact the western slope of the Ashpit. <br /> Vector Engineering,Inc. Observed placement and compaction of the subgrade material. CQA performed <br /> density tests on the subgrade material with all tests passing the required specifications. Guinn was notified <br /> that the GDM material meet specifications for sieve analysis. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: YS <br />