My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
ARCHIVED REPORTS_1999_1
EnvironmentalHealth
>
EHD Program Facility Records by Street Name
>
A
>
AUSTIN
>
9999
>
4400 - Solid Waste Program
>
PR0440005
>
Archived Reports
>
ARCHIVED REPORTS_1999_1
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/17/2020 3:53:20 PM
Creation date
7/3/2020 10:47:55 AM
Metadata
Fields
Template:
EHD - Public
ProgramCode
4400 - Solid Waste Program
File Section
ARCHIVED REPORTS
FileName_PostFix
1999_1
RECORD_ID
PR0440005
PE
4433
FACILITY_ID
FA0004516
FACILITY_NAME
FORWARD DISPOSAL SITE
STREET_NUMBER
9999
STREET_NAME
AUSTIN
STREET_TYPE
RD
City
MANTECA
Zip
95336
APN
20106001-3, 5
CURRENT_STATUS
01
SITE_LOCATION
9999 AUSTIN RD
P_LOCATION
99
P_DISTRICT
004
QC Status
Approved
Scanner
SJGOV\rtan
Supplemental fields
FilePath
\MIGRATIONS\SW\SW_4433_PR0440005_9999 AUSTIN_1999_1.tif
Tags
EHD - Public
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
1129
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
06/01/99 Construction Field Report Job No.986011.0: <br /> DFR No. 16 VECTOR. ENGINEERING, INC. Page No. <br /> i <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.. <br /> Forward Landfill Allied Waste 16 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Manteca,CA Butch Ste ' Jr. 6-1-99 Tuesda <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott nEd <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy clay [Clear.Warm FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 140G Grader,3-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator,966D Cat loader,Water Track,815F Cat <br /> S foot C2.m2actor. Griffin:2 Water trucks,WR2500,RS650 mixers_ Allied:D4, 140G Grader, Smooth Drum Roller. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 9 total Dewalt Crew: 2 total Griffin Crew 4 total <br /> Allied Crew: 2 total <br /> Guinn Construction has Griffin on site to start mixing the clay material. Griffin soils stabilization started the <br /> clay mix today utilizing 2 mixers and 2 water trucks. Grim made 1 pass with a water truck hooked up to the <br /> I'mixer for moisture conditioning of the material as it is being processed. A 2nd pass by the 2nd mixer with <br /> out water for remix. Guinn utilized 2—633 to place the on site material .75' then the 623 placed the.25' of <br /> clay material. 4 lifts were mixed totaling approximately 4'at 110'-150 X 250'-300'. Guinn is excavating the <br /> access ramp and the cell floor at the eastern toe. Guinn has the D6R ripping the subgrade material. The <br /> grader is cutting the south 2:1 slope and grading on the stockpile. Guinn utilized 2-633/1-623 paddle wheels <br /> to excavate and haul the material that is suitable for the clay admixture to the appropriate stockpile. Dewalt <br /> is on site resetting cut stakes in the southeastern comer of the cell and checking the liner tie in elevations for <br /> the cell flow and elevation. Dewalt set laser points on the cell floor to control the 2%grade. <br /> Allied Waste continued to place garbage on the southeast edge of the eastern slope with daily cover material. <br /> Allied continued to construct the anchor trench area on the slopes southern edge of cell WMU D-99. <br /> Vector Engineering, Inc. Observed excavation and stockpiling materials for clay mixture. Pulled a sample <br /> and shipped it to Vector Engineering,Inc. for barge Scale Direct Shear testing. CQA pulled a sample for a <br /> compaction curve. CQA pulled several moisture samples on the clay mix. Tested subgrade material <br /> compaction on the access ramp northern berm with passing results. <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: <br />
The URL can be used to link to this page
Your browser does not support the video tag.