06/29/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 36 VECTOR ENGINEERING, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report Sequence No.: <br /> Forward Landfill Allied Waste 36 <br /> Location Of Work: Owner's Or Client's Representative: Date: Day Of Week: <br /> Manteca,CA Butch Stef ' Jr. 6-29-99 Tuesda <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott Purdy <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician/Technician: <br /> Tan White Clay Clear Hot FRANK DELL-ERA <br /> ANTONIO HENRI UEZ <br /> Equipment used: <br /> Guinn: 140G Grader,3-633/1-623 Paddle Wheels,D4H Cat Dozer,135H Cat Dozer,320L Cat Excavator,966D Cat loader,Water <br /> Truck,CS 563C Cat Smooth Drum roller. Allied:Water Truck,Forklift. GSE:544E John Deere Loader, Gradall. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew. 5 total GSE Crew: 12 total Allied Crew: 1 total <br /> Guinn continues to have the water truck maintain moisture in the clay on the cell floor and performing dust <br /> control all over the site. Guinn started making all of the necessary repairs to the subgrade materials. Guinn <br /> has laborers on site raking the slopes and removing any unsuitable materials found. Guinn has the grader <br /> working on the drop inlet to the southeast comer of cell WMU D-99. Guinn unloaded a load of HDPE pipe <br /> for the LCRS system and the Hancor solid and perforated pipe for the subdrain under the southern roadway. <br /> Guinn rented a vibratory plate to compact the liner tie in edge from the first bench down the slope to the cell <br /> floor. <br /> GSE continues to fill sandbags for temporary anchorage. GSE continues to stage GCL liner material on the <br /> top of the eastern slope of cell WMU D-99. GSE placed sandbags on the cell floor for future use. GSE <br /> unloaded 1 load of GCL material. <br /> Allied continues to perform dust control on lay down area. <br /> Vector Engineering,Inc. Attended construction meeting with representatives of Allied and Guinn <br /> construction. CQA took Guinns foreman on a walk through of the areas needing repairs or materials <br /> removed on the slopes and the benches. <br /> Observed unloading and logged in HDPE pipe. All pipe is on site except the cross for the LCRS West End <br /> tie in to the sump. Liner material. <br /> Material Delivered Total fl Delivered Total W Delivered to Date <br /> HDT 60 mil 105,300 <br /> HME 60 mil 169,200 <br /> HST 60 mil 378,000 <br /> Geonet 71,400 <br /> Geotextile 81,000 <br /> Geocom osite Single sided 210,000 <br /> Geocom osite Double sided 119,000 <br /> GCL 31,500 184,800 <br /> File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: <br />