TZE 'TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 23 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste June 14, 2006 Wednesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Dort tu-c I Cloudy, breezy(W), high 50's to mid 80's Mike Strobel <br /> Equipment on site: <br /> 3x637 scrapers, D6 dozer, 815 compactor, water truck, excavator,rock truck, loader, backhoe <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Continued placement of Subgrade soils outside the side project area on the east side of FU-06 and <br /> minor fill to finish grade on the east floor area. <br /> 2. Start cut at the south end of FU-06; material taken to east floor areas. <br /> 3. Start shaping the central floor area; material taken to east floor areas. <br /> 4. Contractor continued butt-fusion welding the 3" diameter perforated HDPE LCRS pipes. <br /> II. Testing <br /> 1. Performed 4 FDT's in compacted Subgrade; tests SG-70 through SG-73. All tests passed. <br /> III. Conversations <br /> • None listed. <br /> Prepared y. Reviewed By: <br /> 1 of 1 4/23/03,Rev.0 <br />