3.3 BORROW AREA OPERATION <br /> A. All borrow areas shall be kept neat and orderly. Work areas in a systematic <br /> manner. Keep borrow areas graded to drain and take all necessary precautions to <br /> minimize erosion. The EARTHWORK CONTRACTOR shall review the <br /> excavation plan with the QA/QC CONSULTANT prior to any excavation from <br /> borrow areas. Leave all surplus material in the borrow area. Maintain access <br /> roads as necessary at EARTHWORK CONTRACTOR's expense. Excavation at <br /> the borrow areas shall be limited to the elevations shown on the drawings and <br /> shall be excavated to permit the completed area to slope to drain to the <br /> surrounding area after completion of all Work. <br /> A. The EARTHWORK CONTRACTOR shall selectively stockpile the onsite fine <br /> grained material to use as Clay Liner Material. The EARTHWORK <br /> CONTRACTOR shall also selectively stockpile material appropriate for use as <br /> protective operations layer. <br /> C. Soils to be excavated are variable. Soil suitable for use as the Clay Liner material, <br /> Clay Earthfill or Protective Operations Layer may only be encountered in thin <br /> intermittent seams. <br /> D. The EARTHWORK CONTRACTOR shall make all reasonable efforts to <br /> determine the type of soil being excavated at all times. Equipment operators or <br /> the EARTHWORK CONTRACTOR's representative directing excavation shall <br /> have sufficient knowledge and understanding of soil classifications to determine <br /> general soil type. <br /> E. If vegetative material or topsoil is encountered in the borrow area, it shall be <br /> removed and stockpiled at an onsite location, as directed by the OWNER. <br /> 3.4 EXCAVATION <br /> A. Perform all excavation of every description, regardless of the type, nature, or <br /> condition of material encountered, as specified, shown, or required to accomplish <br /> the construction. Transport excavated material to where it will be placed or to the <br /> designated stockpile area. Any refuse excavated shall be placed in active landfill <br /> areas, as directed by the OWNER. <br /> B. The EARTHWORK CONTRACTOR shall selectively stockpile the onsite fine- <br /> grained material to use as Clay Liner or Clay Earthfill Material. The <br /> EARTHWORK CONTRACTOR shall also selectively stockpile material <br /> appropriate for use as protective operations layer. <br /> C. Soils to be excavated are variable. Fine-grained material suitable for use as the <br /> Clay Liner or Clay Earthfill material may only be encountered in thin intermittent <br /> seams. The clay liner material shall be first obtained from the eastern onsite <br /> borrow source until a sufficient amount of material has been obtained or there is <br /> no suitable clay liner material remaining in the eastern borrow area. Clay liner <br /> Forward Landfill WMU FU-14 <br /> 02300 10 EARTHWORK <br />