My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
SU0013949
EnvironmentalHealth
>
EHD Program Facility Records by Street Name
>
S
>
STEWART
>
2100
>
2600 - Land Use Program
>
RIVER ISLAND DSEIR
>
SU0013949
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/4/2021 1:39:33 PM
Creation date
2/22/2021 9:18:05 AM
Metadata
Fields
Template:
EHD - Public
ProgramCode
2600 - Land Use Program
RECORD_ID
SU0013949
PE
2686
FACILITY_NAME
RIVER ISLAND DSEIR
STREET_NUMBER
2100
STREET_NAME
STEWART
City
LATHROP
Zip
95304-
APN
21325004
ENTERED_DATE
2/22/2021 12:00:00 AM
SITE_LOCATION
2100 STEWART
RECEIVED_DATE
2/19/2021 12:00:00 AM
P_LOCATION
07
P_DISTRICT
005
QC Status
Approved
Scanner
SJGOV\sshih
Tags
EHD - Public
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
1228
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
3.2 New Phase 2 nomenclature <br /> 3.21 Alternative 6 (Alt 6) <br /> As for Phase 1 nomenclature, Alternative 6 (Alt 6) refers to the number of active stormwater evacuation <br /> pumps. For this new alternative, it does not only refer to the pump station in watershed A but also the one <br /> in watershed BIC. <br /> • Alt 6 has an equivalent of 8 active unit pumps: 2 at pump station A (by lake 3), 68 (3 actual <br /> pumps) at Phase 2 pump station in watershed B/C (between lakes 12, 19 and 22). <br /> The pumps (for models with pumping) are modelled with pumps "Rated By Static Head" meaning that a <br /> pump that pumps according to the head at the upstream node using a multi-point pump curve and starting <br /> and stopping elevations. The pump rate was set to 12.5cfs for all static head values meaning that all <br /> pumps would pump 12.5cfs (each)whenever on9. The start and stop elevations for the pumps at all pump <br /> stations: <br /> • Pump 1: Start 5.3 Stop: 5.1 <br /> • Pump 2: Start 5.5 Stop: 5.1 <br /> • Pump 3: Start 5.7 Stop: 5.1 (Phase 2 pump station only) <br /> • Pump 4: Start 5.3 Stop: 5.1 (Phase 2 pump station only) <br /> • Pump 5: Start 5.5 Stop: 5.1 (Phase 2 pump station only) <br /> • Pump 6: Start 5.7 Stop: 5.1 (Phase 2 pump station only) <br /> 3.2.2 Lake L <br /> The designation "L" refer to the path the stormwater from watershed A/phase 1 is evacuated. <br /> • L: Water from lake 3 in watershed A is pumped into lake 25 located in watershed B. <br /> 3.2.3 Version 2.0(V20) <br /> The designation V20 refers to the finalized lake- and pump station connection pipes layout for phase 2. <br /> While this report only presents the results for this layout, the designation is included to differentiate <br /> between pervious model configurations presented in earlier revisions of the River Islands Phase 2 <br /> Stormwater Report. In Appendix C the layout of the lake interconnection pipes for this model are shown <br /> and Figure 2-1 shows the same layout in the XPSWMM interface. <br /> 3.2.4 Contributory(ca) and Lake (la) drainage areas <br /> • ca: Approximated contributory drainage area used for phase 2 lake hydrograph as described in <br /> section 2.4.1. <br /> • la: Contributory drainage area scaled relative to the lake size compared to total lake area in <br /> phase 2 as described in section 2.4.2. <br /> 3.2.5 Phase 2 Pump Station (PS) <br /> • PS: Assumes there is a lake interconnection pipe (flat gravity pipe) between lake 12 in Phase 1 <br /> and the wet well at the Phase 2 pump station in watershed B/C10. <br /> $As described in Section 1.2, the actual Phase 2 Pump station will have 3 active pumps with twice the flow(25cfs)from described <br /> here (12.5cfs) as well as one standby pump. The 12.5cfs unit pumps are used for correlation with the other pump station (pump <br /> station A in Phase 1). <br /> 9 idem <br /> 10 Note that the 'Phase 2 Pump Station" (PS) configuration is different from the Phase 1 model configuration "Farm Pump" (FP) <br /> where a temporary pump is evacuating stormwater from lake 12. See River Islands Phase 1 Stormwater Mitigation report dated April <br /> 2020 for more information on the"Farm Pump"model configuration. <br /> River Islands Phase 2 Stormwater Mitigation Rev 2 18 Owmft_._.� <br /> PACE <br />
The URL can be used to link to this page
Your browser does not support the video tag.