Commissioning Plan, June 24, 2018 <br />■ All fenestration must be completely installed with all labels, protective films, etc. <br />removed and transparent surfaces cleaned. <br />o Criteria for acceptable performance <br />■ Light levels at or above required levels when spaces are occupied <br />■ LCP functions per design <br />■ Occupancy sensors turn lights on/off per design <br />■ Daylighting controls dim or turn lights on/off per design without compromising <br />required light levels <br />o Water Heating System <br />o Original design intent: An electric water heater and circulation pump will serve the <br />bathrooms and a gas water heater and circulation pump will serve the kitchen. Hot <br />water temperatures are designed to range between 105°F and 120°F. <br />o Equipment and systems to be tested: <br />■ EWH-1, Electric Water Heater serving bathrooms <br />■ DWH-1, Gas Water Heater serving kitchen <br />■ CP -1, Domestic Hot Water Circulation Pump <br />■ CP -2, Domestic Hot Water Circulation Pump <br />o Functions to be tested <br />■ Hot water temperature <br />■ Circulation pump timers <br />o Conditions of tests: <br />Water heaters, circulation pumps, timers/controls, and all fixtures requiring <br />hot water must be completely installed with drains and hot water supply fully <br />operational. <br />o Criteria for acceptable performance <br />■ Hot water temperature at all outlets within acceptable temperature range. <br />■ Circulation pump timer functioning per design. <br />o Renewable Energy Systems: Not included in project. <br />o Landscape Irrigation System: <br />■ Original design intent: All new landscape irrigation installed as part of this project will <br />be via drip irrigation with irrigation controls incorporating either weather -based or soil <br />moisture -based sensors. <br />o Equipment and systems to be tested: <br />■ Drip irrigation controller/timer <br />o Functions to be tested <br />■ Need -based irrigation based on weather -based or soil moisture -based <br />sensors. <br />o Conditions of tests.- <br />Landscaping <br />ests: <br />Landscaping and landscape irrigation system must be completely installed <br />and irrigation system must be fully operational. <br />o Criteria for acceptable performance: System will provide Irrigation only when needed <br />per sensors. <br />Water Reuse Systems: Not included in project. <br />All Systems: <br />o Site Observation: The Commissioning Provider will make periodic visits to witness <br />installation of equipment and systems. All visits will be planned in advance, will have <br />a specific agenda and will be coordinated with the general contractor. The general <br />contractor will keep the Commissioning Provider apprised of any field changes which <br />may affect commissioned equipment or the commissioning schedule. <br />o Prior to start-up, installing contractor must verify installation to general contractor in <br />writing. General contractor to provide a copy of written verification to Commissioning <br />Provider. <br />3 of 8 <br />